Data centers and new power in Lubbock County, TX

426 MW of new power is waiting to connect to the grid in Lubbock County, TX — 2 active requests. Typical wait: 5.1 years. 2 projects are built, 9 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Lubbock County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Lubbock County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Lubbock County right now.

426 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 341,000 homes use.
410 MW
has actually been built
2 projects switched on so far.
5.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 12%
  • Still waiting 12%
  • Withdrawn 53%
  • Paused 24%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Lubbock County.

What kind of power is asking to connect

  • Batteries 53%
  • Solar 47%

By capacity requested. Data as of 14 October 2026.

All the numbers

17 requests ever filed
Pending applications
2
of 17 ever filed
Capacity queued
426 MW
requested, not committed
Already built
410 MW
2 projects connected
Built vs decided
18.2%
9 withdrawn
Median wait
5.1 yr
for applications still pending
Connected capacity
874 MW
indicator, see note

Source: interconnection queues published by ERCOT, SPP. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built2410 MW11.8%
Still waiting2426 MW11.8%
Withdrawn9934 MW52.9%
Paused4—23.5%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries1226 MW
Solar1200 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
GEN-2009-002Natural gas306 MWwithdrawn2009-01SPP
Staked Plains BESSBatteries255 MWsuspended2023-03ERCOT
GEN-2022-141Batteries250 MWwithdrawn2023-02SPP
Dunkel BESSBatteries226 MWactive2023-01ERCOT
GEN-2011-045Natural gas205 MWcompleted2011-09SPP
GEN-2010-006Natural gas205 MWcompleted2010-03SPP
GEN-2020-060Solar200 MWactive2020-04SPP
GEN-2024-356Batteries199 MWwithdrawn2025-03SPP
GEN-2009-001Natural gas128 MWwithdrawn2009-01SPP
R MassengaleNatural gas58 MWsuspended2018-09ERCOT
GEN-2007-031Wind51 MWwithdrawn2007-07SPP
Ty CookeNatural gas33 MWsuspended2020-08ERCOT
BrandonNatural gas21 MWsuspended2018-09ERCOT
BrandonNatural gas—withdrawn—ERCOT
R MassengaleNatural gas—withdrawn—ERCOT

How Lubbock County compares

#676 in the US · #155 in TX

Lubbock County ranks #676 of 1,607 US counties by power waiting to connect, and #155 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Lubbock County

How long does it take to get power for a data center in Lubbock County, TX?

The median wait for a project still in the interconnection queue in Lubbock County is 5.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Lubbock County have reached energization and 9 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Lubbock County, TX?

426 MW is currently requested across 2 active interconnection requests, and 410 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Lubbock County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Lubbock County — ERCOT, SPP — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Lubbock County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Lubbock County on the map County reports All of Texas