Data centers and new power in Kent County, TX
822 MW of new power is waiting to connect to the grid in Kent County, TX — 4 active requests. Typical wait: 4.8 years. 2 projects are built, 1 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Kent County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Kent County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Kent County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Kent County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
8 requests ever filed
Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 2 | 455 MW | 25.0% |
| Still waiting | 4 | 822 MW | 50.0% |
| Withdrawn | 1 | 0 MW | 12.5% |
| Paused | 1 | — | 12.5% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar | 3 | 563 MW |
| Batteries | 1 | 259 MW |
Key dates for projects here
no dated windows published
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| ERCOT | ERCOT Batch 1 large load interconnection - applications not yet dated Successor cycle to Batch Zero under PGRR145. | No date published yet | confirmed source |
| ERCOT | ERCOT generation interconnection — rolling Not FERC-jurisdictional. | Open all year — no cut-off | unconfirmed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
| ERCOT | Texas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a)) All new large-load interconnections must carry ERCOT-controlled curtailment equipment. | Open all year — no cut-off | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 8 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Lake Henry Wind | Wind | 305 MW | suspended | 2022-09 | ERCOT |
| Jay Flat BESS | Batteries | 259 MW | active | 2027-01 | ERCOT |
| Texas Solar Nova | Solar | 254 MW | completed | 2015-11 | ERCOT |
| Clairemont Solar 1 | Solar | 252 MW | active | 2027-01 | ERCOT |
| Texas Solar Nova 2 | Solar | 201 MW | completed | 2019-06 | ERCOT |
| TEXAS SOLAR NOVA 3 | Solar | 200 MW | active | 2022-01 | ERCOT |
| Carpet Tech Solar One | Solar | 111 MW | active | 2028-01 | ERCOT |
| Lake Henry Wind | Wind | — | withdrawn | — | ERCOT |
How Kent County compares
#463 in the US · #138 in TX
Kent County ranks #463 of 1,607 US counties by power waiting to connect, and #138 of 183 in Texas.
| County | Waiting | Capacity queued |
|---|---|---|
| Pecos County | 55 | 21.2 GW |
| Brazoria County | 55 | 11.7 GW |
| Milam County | 33 | 9.2 GW |
| Wharton County | 40 | 9.1 GW |
| Jack County | 18 | 8.6 GW |
| Hill County | 23 | 8.0 GW |
| Reeves County | 21 | 7.8 GW |
| Wilbarger County | 20 | 7.0 GW |
Common questions about power in Kent County
How long does it take to get power for a data center in Kent County, TX?
The median wait for a project still in the interconnection queue in Kent County is 4.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Kent County have reached energization and 1 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Kent County, TX?
822 MW is currently requested across 4 active interconnection requests, and 455 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Kent County, TX a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Kent County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.