Data centers and new power in Kenedy County, TX

1.3 GW of new power is waiting to connect to the grid in Kenedy County, TX — 4 active requests. 1 projects are built, 2 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Kenedy County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Kenedy County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Kenedy County right now.

1.3 GW
of new power is waiting to connect
4 projects asked. Not yet approved. Roughly what 1 million homes use.
201 MW
has actually been built
1 projects switched on so far.
2
projects gave up
Withdrawn before being built. Normal nationally.

Where every request ever filed here ended up

  • Built 11%
  • Still waiting 44%
  • Withdrawn 22%
  • Paused 22%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Kenedy County.

What kind of power is asking to connect

  • Solar 46%
  • Wind 40%
  • Batteries 14%

By capacity requested. Data as of 14 October 2026.

All the numbers

9 requests ever filed
Pending applications
4
of 9 ever filed
Capacity queued
1.3 GW
requested, not committed
Already built
201 MW
1 projects connected
Built vs decided
33.3%
2 withdrawn
Connected capacity
1.1 GW
indicator, see note

Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built1201 MW11.1%
Still waiting41.3 GW44.4%
Withdrawn248 MW22.2%
Paused2—22.2%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar2609 MW
Wind1523 MW
Batteries1178 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 9 by size
ProjectTypeCapacityStatusFiledQueue
Tall Saddle WindWind523 MWactive2027-01ERCOT
Green Ocelot SolarSolar357 MWactive2028-01ERCOT
Tall Saddle SolarSolar252 MWactive2027-01ERCOT
Gulf Wind 2Wind226 MWsuspended2018-01ERCOT
Stella 1 WindWind201 MWcompleted2013-02ERCOT
Stella 2 WindWind201 MWsuspended2013-06ERCOT
Green Ocelot StorageBatteries178 MWactive2028-01ERCOT
Gulf Wind 2 ExpansionWind48 MWwithdrawn2019-03ERCOT
Gulf Wind 2Wind—withdrawn—ERCOT

How Kenedy County compares

#289 in the US · #106 in TX

Kenedy County ranks #289 of 1,607 US counties by power waiting to connect, and #106 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Kenedy County

How long does it take to get power for a data center in Kenedy County, TX?

We do not yet have a median wait for Kenedy County. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Kenedy County have reached energization and 2 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Kenedy County, TX?

1.3 GW is currently requested across 4 active interconnection requests, and 201 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Kenedy County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Kenedy County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Kenedy County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Kenedy County on the map County reports All of Texas