Data centers and new power in Hansford County, TX

67 MW of new power is waiting to connect to the grid in Hansford County, TX — 1 active requests. Typical wait: 1.4 years. 6 projects are built, 9 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Hansford County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Hansford County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Hansford County right now.

67 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 54,000 homes use.
1.4 GW
has actually been built
6 projects switched on so far.
1.4 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 38%
  • Still waiting 6%
  • Withdrawn 56%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Hansford County.

What kind of power is asking to connect

  • Wind 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

16 requests ever filed
Pending applications
1
of 16 ever filed
Capacity queued
67 MW
requested, not committed
Already built
1.4 GW
6 projects connected
Built vs decided
40.0%
9 withdrawn
Median wait
1.4 yr
for applications still pending
Connected capacity
1.2 GW
indicator, see note

Source: interconnection queues published by SPP. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built61.4 GW37.5%
Still waiting167 MW6.2%
Withdrawn92.1 GW56.2%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Wind167 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
GEN-2006-044Wind370 MWcompleted2006-12SPP
GEN-2022-112Other370 MWwithdrawn2023-02SPP
GEN-2007-042Wind360 MWwithdrawn2007-09SPP
GEN-2010-014Wind359 MWcompleted2010-03SPP
GEN-2009-041Wind300 MWwithdrawn2009-09SPP
GEN-2011-022Wind299 MWcompleted2011-03SPP
GEN-2011-021Wind299 MWwithdrawn2011-03SPP
GEN-2002-008Wind240 MWcompleted2002-07SPP
GEN-2009-018Wind200 MWwithdrawn2009-04SPP
GEN-2014-038Wind200 MWwithdrawn2014-09SPP
GEN-2021-SR5Batteries126 MWwithdrawn2021-05SPP
GEN-2007-039Wind120 MWwithdrawn2007-09SPP
GEN-2021-092Batteries100 MWwithdrawn2021-04SPP
GEN-2025-SR2Wind67 MWactive2025-05SPP
GEN-2002-009Wind67 MWcompleted2002-07SPP

How Hansford County compares

#1161 in the US · #174 in TX

Hansford County ranks #1161 of 1,607 US counties by power waiting to connect, and #174 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Hansford County

How long does it take to get power for a data center in Hansford County, TX?

The median wait for a project still in the interconnection queue in Hansford County is 1.4 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 6 projects in Hansford County have reached energization and 9 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Hansford County, TX?

67 MW is currently requested across 1 active interconnection requests, and 1.4 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Hansford County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Hansford County — SPP — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.