Data centers and new power in Fort Bend County, TX

2.0 GW of new power is waiting to connect to the grid in Fort Bend County, TX — 10 active requests. Typical wait: 1.8 years. 11 projects are built, 10 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Fort Bend County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Fort Bend County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Fort Bend County right now.

2.0 GW
of new power is waiting to connect
10 projects asked. Not yet approved. Roughly what 1.6 million homes use.
1.1 GW
has actually been built
11 projects switched on so far.
1.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 32%
  • Still waiting 29%
  • Withdrawn 29%
  • Paused 9%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Fort Bend County.

What kind of power is asking to connect

  • Batteries 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

34 requests ever filed
Pending applications
10
of 34 ever filed
Capacity queued
2.0 GW
requested, not committed
Already built
1.1 GW
11 projects connected
Built vs decided
52.4%
10 withdrawn
Median wait
1.8 yr
for applications still pending
Connected capacity
7.2 GW
indicator, see note

Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built111.1 GW32.4%
Still waiting102.0 GW29.4%
Withdrawn101.3 GW29.4%
Paused3—8.8%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries102.0 GW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Avalon BESSBatteries522 MWactive2026-01ERCOT
Sibyl Power StationNatural gas299 MWwithdrawn2020-09ERCOT
UNICORN BESSBatteries279 MWactive2027-01ERCOT
Rock Rose BESSBatteries208 MWactive2026-01ERCOT
Bypass BESS IIBatteries206 MWactive2026-01ERCOT
Rowland Solar IISolar203 MWcompleted2020-12ERCOT
Corbin Grid BESSOther203 MWwithdrawn2020-08ERCOT
Elan BESSBatteries203 MWactive2025-01ERCOT
Sibyl Energy StorageOther202 MWwithdrawn2020-12ERCOT
Raoul SolarSolar201 MWwithdrawn2020-10ERCOT
Creekfield SolarSolar161 MWsuspended2020-01ERCOT
Crowned Heron BESSBatteries154 MWactive2024-01ERCOT
Crowned Heron BESS 2Batteries154 MWactive2024-01ERCOT
Rabbs Power StationNatural gas153 MWcompleted2018-12ERCOT
Sibyl 2 Energy StorageOther152 MWwithdrawn2021-05ERCOT

How Fort Bend County compares

#192 in the US · #78 in TX

Fort Bend County ranks #192 of 1,607 US counties by power waiting to connect, and #78 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Fort Bend County

How long does it take to get power for a data center in Fort Bend County, TX?

The median wait for a project still in the interconnection queue in Fort Bend County is 1.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 11 projects in Fort Bend County have reached energization and 10 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Fort Bend County, TX?

2.0 GW is currently requested across 10 active interconnection requests, and 1.1 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Fort Bend County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Fort Bend County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.