Data centers and new power in Ector County, TX

4.2 GW of new power is waiting to connect to the grid in Ector County, TX — 21 active requests. Typical wait: 2.8 years. 7 projects are built, 12 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Ector County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Ector County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Ector County right now.

4.2 GW
of new power is waiting to connect
21 projects asked. Not yet approved. Roughly what 3.3 million homes use.
526 MW
has actually been built
7 projects switched on so far.
2.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 17%
  • Still waiting 50%
  • Withdrawn 29%
  • Paused 5%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Ector County.

What kind of power is asking to connect

  • Solar 61%
  • Batteries 37%
  • Natural gas 3%

By capacity requested. Data as of 14 October 2026.

All the numbers

42 requests ever filed
Pending applications
21
of 42 ever filed
Capacity queued
4.2 GW
requested, not committed
Already built
526 MW
7 projects connected
Built vs decided
36.8%
12 withdrawn
Median wait
2.8 yr
for applications still pending
Connected capacity
2.9 GW
indicator, see note

Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built7526 MW16.7%
Still waiting214.2 GW50.0%
Withdrawn123.8 GW28.6%
Paused2—4.8%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar112.5 GW
Batteries91.5 GW
Natural gas1123 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
GEN-2010-060Natural gas992 MWwithdrawn2010-12SPP
GEN-2008-135Natural gas531 MWwithdrawn2008-12SPP
GEN-2008-136Natural gas531 MWwithdrawn2008-12SPP
GEN-2010-059Natural gas516 MWwithdrawn2010-12SPP
Gypsum Plains SolarSolar503 MWactive2028-01ERCOT
GEN-2001-008Natural gas500 MWwithdrawn2001-03SPP
Jackrabbit Flats SolarSolar401 MWactive2030-01ERCOT
Greyhound SolarSolar335 MWactive2021-01ERCOT
Van Zandt Energy StorageBatteries256 MWactive2025-01ERCOT
Rockhound SolarSolar250 MWwithdrawn2019-02ERCOT
Velociraptor BESS IIBatteries246 MWactive2028-01ERCOT
Velociraptor BESS IBatteries246 MWactive2027-01ERCOT
Velociraptor Solar IISolar242 MWactive2028-01ERCOT
Velociraptor Solar ISolar242 MWactive2022-01ERCOT
Gypsum Plains StorageBatteries211 MWactive2028-01ERCOT

How Ector County compares

#71 in the US · #34 in TX

Ector County ranks #71 of 1,607 US counties by power waiting to connect, and #34 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Ector County

How long does it take to get power for a data center in Ector County, TX?

The median wait for a project still in the interconnection queue in Ector County is 2.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 7 projects in Ector County have reached energization and 12 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Ector County, TX?

4.2 GW is currently requested across 21 active interconnection requests, and 526 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Ector County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Ector County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.