Concho County, TX interconnection queue
6 interconnection applications are pending in Concho County, TX, requesting 1.5 GW of new generating capacity, as of 15 August 2026. 5 projects have been built here and 4 have been withdrawn since 2015.
Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Concho County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 4 | 969 MW |
| Wind | 1 | 379 MW |
| Battery | 1 | 162 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 5 | 1.0 GW | 31.2% |
| Still pending | 6 | 1.5 GW | 37.5% |
| Withdrawn | 4 | 110 MW | 25.0% |
| Suspended | 1 | — | 6.2% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Paint Rock Wind | Wind | 379 MW | active | 2027-01 | ERCOT |
| Maverick Creek I Wind | Wind | 373 MW | completed | 2018-01 | ERCOT |
| Lucy Solar | Solar | 352 MW | active | 2025-01 | ERCOT |
| Trail Ranch Solar 1 | Solar | 302 MW | active | 2029-01 | ERCOT |
| Galloway Solar | Solar | 250 MW | completed | 2017-08 | ERCOT |
| Concho Pearl Solar | Solar | 172 MW | active | 2025-01 | ERCOT |
| Concho Pearl Storage | Battery | 162 MW | active | 2025-01 | ERCOT |
| Cactus Flats Wind | Wind | 148 MW | completed | 2015-02 | ERCOT |
| Cherry Sage Solar 1 SLF | Solar | 143 MW | active | 2028-01 | ERCOT |
| Maverick Creek II Wind | Wind | 119 MW | completed | 2018-01 | ERCOT |
| Galloway 2 Solar | Solar | 114 MW | completed | 2019-08 | ERCOT |
| Galloway 2 Storage | Other | 110 MW | withdrawn | 2019-08 | ERCOT |
| Old Sorrell Energy Storage | Battery | 43 MW | suspended | 2023-06 | ERCOT |
| Old Sorrell Energy Storage | Solar | — | withdrawn | — | ERCOT |
| Operation Sunshine Storage | Solar | — | withdrawn | — | ERCOT |
How this county ranks
Concho County ranks #256 of 1,607 US counties by capacity currently queued, and #98 of 183 in Texas.
Other Texas counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Pecos County | 55 | 21.2 GW |
| Brazoria County | 55 | 11.7 GW |
| Milam County | 33 | 9.2 GW |
| Wharton County | 40 | 9.1 GW |
| Jack County | 18 | 8.6 GW |
| Hill County | 23 | 8.0 GW |
| Reeves County | 21 | 7.8 GW |
| Wilbarger County | 20 | 7.0 GW |
Go deeper on Concho County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.