Data centers and new power in Collin County, TX

972 MW of new power is waiting to connect to the grid in Collin County, TX — 5 active requests. Typical wait: 1.8 years. 3 projects are built, 2 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Collin County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Collin County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Collin County right now.

972 MW
of new power is waiting to connect
5 projects asked. Not yet approved. Roughly what 777,000 homes use.
143 MW
has actually been built
3 projects switched on so far.
1.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 30%
  • Still waiting 50%
  • Withdrawn 20%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Collin County.

What kind of power is asking to connect

  • Batteries 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

10 requests ever filed
Pending applications
5
of 10 ever filed
Capacity queued
972 MW
requested, not committed
Already built
143 MW
3 projects connected
Built vs decided
60.0%
2 withdrawn
Median wait
1.8 yr
for applications still pending
Connected capacity
590 MW
indicator, see note

Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built3143 MW30.0%
Still waiting5972 MW50.0%
Withdrawn2253 MW20.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries5972 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 10 by size
ProjectTypeCapacityStatusFiledQueue
Drake BESSBatteries257 MWactive2025-01ERCOT
Little Ridge StorageBatteries252 MWactive2025-01ERCOT
BRP Tigris BESSOther202 MWwithdrawn2021-06ERCOT
Purple Sage BESS 1Batteries156 MWactive2025-01ERCOT
Purple Sage BESS 2Batteries156 MWactive2025-01ERCOT
Bufflehead BESSBatteries150 MWactive2024-01ERCOT
Wigeon Whistle BESSOther123 MWcompleted2022-04ERCOT
Mallard BESS IIOther50 MWwithdrawn—ERCOT
Farmersville West BESS 1Other10 MWcompleted2022-11ERCOT
Farmersville West BESS 2Batteries10 MWcompleted2023-06ERCOT

How Collin County compares

#383 in the US · #125 in TX

Collin County ranks #383 of 1,607 US counties by power waiting to connect, and #125 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Collin County

How long does it take to get power for a data center in Collin County, TX?

The median wait for a project still in the interconnection queue in Collin County is 1.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 3 projects in Collin County have reached energization and 2 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Collin County, TX?

972 MW is currently requested across 5 active interconnection requests, and 143 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Collin County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Collin County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Collin County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Collin County on the map County reports All of Texas