Data centers and new power in Calhoun County, TX

850 MW of new power is waiting to connect to the grid in Calhoun County, TX — 4 active requests. Typical wait: 3.8 years. 2 projects are built, 3 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Calhoun County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Calhoun County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Calhoun County right now.

850 MW
of new power is waiting to connect
4 projects asked. Not yet approved. Roughly what 680,000 homes use.
340 MW
has actually been built
2 projects switched on so far.
3.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 22%
  • Still waiting 44%
  • Withdrawn 33%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Calhoun County.

What kind of power is asking to connect

  • Solar 64%
  • Batteries 36%

By capacity requested. Data as of 14 October 2026.

All the numbers

9 requests ever filed
Pending applications
4
of 9 ever filed
Capacity queued
850 MW
requested, not committed
Already built
340 MW
2 projects connected
Built vs decided
40.0%
3 withdrawn
Median wait
3.8 yr
for applications still pending
Connected capacity
1.8 GW
indicator, see note

Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built2340 MW22.2%
Still waiting4850 MW44.4%
Withdrawn3401 MW33.3%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar2542 MW
Batteries2308 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 9 by size
ProjectTypeCapacityStatusFiledQueue
HyFuels Green Lake SolarSolar347 MWactive2026-01ERCOT
Formosa IncreaseNatural gas240 MWcompleted2016-09ERCOT
Wolfram StorageBatteries207 MWactive2027-01ERCOT
Seaside SolarSolar200 MWwithdrawn2020-12ERCOT
Tres Bahias SolarSolar195 MWactive2020-01ERCOT
Canvasback BESSOther150 MWwithdrawn2022-08ERCOT
Vaca StorageBatteries101 MWactive2023-01ERCOT
VictPortNatural gas100 MWcompleted2016-04ERCOT
Canvasback II BESSOther50 MWwithdrawn—ERCOT

How Calhoun County compares

#452 in the US · #135 in TX

Calhoun County ranks #452 of 1,607 US counties by power waiting to connect, and #135 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Calhoun County

How long does it take to get power for a data center in Calhoun County, TX?

The median wait for a project still in the interconnection queue in Calhoun County is 3.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Calhoun County have reached energization and 3 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Calhoun County, TX?

850 MW is currently requested across 4 active interconnection requests, and 340 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Calhoun County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Calhoun County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Calhoun County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Calhoun County on the map County reports All of Texas