Data centers and new power in Bailey County, TX

400 MW of new power is waiting to connect to the grid in Bailey County, TX — 1 active requests. Typical wait: 1.6 years. 1 projects are built, 13 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Bailey County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Bailey County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Bailey County right now.

400 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 320,000 homes use.
148 MW
has actually been built
1 projects switched on so far.
1.6 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 7%
  • Still waiting 7%
  • Withdrawn 87%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Bailey County.

What kind of power is asking to connect

  • Wind 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

15 requests ever filed
Pending applications
1
of 15 ever filed
Capacity queued
400 MW
requested, not committed
Already built
148 MW
1 projects connected
Built vs decided
7.1%
13 withdrawn
Median wait
1.6 yr
for applications still pending
Connected capacity
148 MW
indicator, see note

Source: interconnection queues published by SPP. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built1148 MW6.7%
Still waiting1400 MW6.7%
Withdrawn132.6 GW86.7%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Wind1400 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
GEN-2023-240Solar550 MWwithdrawn2023-10SPP
GEN-2024-109Wind400 MWactive2025-03SPP
GEN-2023-158Solar335 MWwithdrawn2023-10SPP
GEN-2017-190Solar300 MWwithdrawn2017-11SPP
GEN-2023-195Solar250 MWwithdrawn2023-10SPP
GEN-2017-039Wind200 MWwithdrawn2017-05SPP
GEN-2023-159Batteries170 MWwithdrawn2023-10SPP
GEN-2005-010Wind160 MWwithdrawn2005-07SPP
GEN-2007-034Wind150 MWwithdrawn2007-08SPP
GEN-2023-196Batteries150 MWwithdrawn2023-10SPP
GEN-2013-027Wind148 MWcompleted2013-09SPP
GEN-2016-078Solar108 MWwithdrawn2016-06SPP
GEN-2016-089Solar100 MWwithdrawn2016-09SPP
GEN-2014-009Wind84 MWwithdrawn2014-03SPP
GEN-2018-085Batteries74 MWwithdrawn2018-11SPP

How Bailey County compares

#693 in the US · #156 in TX

Bailey County ranks #693 of 1,607 US counties by power waiting to connect, and #156 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Bailey County

How long does it take to get power for a data center in Bailey County, TX?

The median wait for a project still in the interconnection queue in Bailey County is 1.6 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Bailey County have reached energization and 13 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Bailey County, TX?

400 MW is currently requested across 1 active interconnection requests, and 148 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Bailey County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Bailey County — SPP — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Bailey County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.