Data centers and new power in Armstrong County, TX

3.3 GW of new power is waiting to connect to the grid in Armstrong County, TX — 5 active requests. Typical wait: 1.8 years. 1 projects are built, 0 withdrawn. Data as of 14 October 2026.

Live here?

How far is it from your house?

Goodnight, run by Google, is in Armstrong County.

1 public schools are within 5 miles of it, 1 within one mile. Counted from the facility, not from any home. School list: US Department of Education.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Armstrong County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Armstrong County right now.

3.3 GW
of new power is waiting to connect
5 projects asked. Not yet approved. Roughly what 2.6 million homes use.
258 MW
has actually been built
1 projects switched on so far.
1.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 14%
  • Still waiting 71%
  • Paused 14%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Armstrong County.

What kind of power is asking to connect

  • Wind 52%
  • Batteries 32%
  • Solar 15%

By capacity requested. Data as of 14 October 2026.

All the numbers

7 requests ever filed
Pending applications
5
of 7 ever filed
Capacity queued
3.3 GW
requested, not committed
Already built
258 MW
1 projects connected
Built vs decided
100.0%
0 withdrawn
Median wait
1.8 yr
for applications still pending
Connected capacity
266 MW
indicator, see note

Source: interconnection queues published by ERCOT. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built1258 MW14.3%
Still waiting53.3 GW71.4%
Withdrawn00 MW0.0%
Paused1—14.3%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Wind31.7 GW
Batteries11.0 GW
Solar1504 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
ERCOTERCOT Batch 1 large load interconnection - applications not yet dated
Successor cycle to Batch Zero under PGRR145.
No date published yetconfirmed source
ERCOTERCOT generation interconnection — rolling
Not FERC-jurisdictional.
Open all year — no cut-offunconfirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
ERCOTTexas SB 6 - large load curtailment protocol and equipment (PURA section 39.170(a))
All new large-load interconnections must carry ERCOT-controlled curtailment equipment.
Open all year — no cut-offconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 7 by size
ProjectTypeCapacityStatusFiledQueue
Zeus Armstrong BESSBatteries1.0 GWactive2025-01ERCOT
Complex Serenity WindWind971 MWactive2028-01ERCOT
Zeus Armstrong SolarSolar504 MWactive2025-01ERCOT
Serenity WindWind473 MWactive2027-01ERCOT
Goodnight Wind IIWind261 MWactive2023-01ERCOT
Goodnight WindWind258 MWcompleted2012-07ERCOT
Armstrong WindWind253 MWsuspended2016-05ERCOT

How Armstrong County compares

#100 in the US · #47 in TX

Armstrong County ranks #100 of 1,607 US counties by power waiting to connect, and #47 of 183 in Texas.

CountyWaitingCapacity queued
Pecos County5521.2 GW
Brazoria County5511.7 GW
Milam County339.2 GW
Wharton County409.1 GW
Jack County188.6 GW
Hill County238.0 GW
Reeves County217.8 GW
Wilbarger County207.0 GW

Common questions about power in Armstrong County

How long does it take to get power for a data center in Armstrong County, TX?

The median wait for a project still in the interconnection queue in Armstrong County is 1.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Armstrong County have reached energization and 0 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Armstrong County, TX?

3.3 GW is currently requested across 5 active interconnection requests, and 258 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Armstrong County, TX a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Texas policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Armstrong County — ERCOT — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Armstrong County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Armstrong County on the map County reports All of Texas