Data centers and new power in Jay County, IN

289 MW of new power is waiting to connect to the grid in Jay County, IN — 3 active requests. Typical wait: 6.2 years. 4 projects are built, 19 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Jay County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Jay County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Jay County right now.

289 MW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 231,000 homes use.
396 MW
has actually been built
4 projects switched on so far.
6.2 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 15%
  • Still waiting 11%
  • Withdrawn 70%
  • Paused 4%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Jay County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

27 requests ever filed
Pending applications
3
of 27 ever filed
Capacity queued
289 MW
requested, not committed
Already built
396 MW
4 projects connected
Built vs decided
17.4%
19 withdrawn
Median wait
6.2 yr
for applications still pending
Connected capacity
273 MW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built4396 MW14.8%
Still waiting3289 MW11.1%
Withdrawn192.1 GW70.4%
Paused1—3.7%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar3289 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Penville-Adams 138 kVSolar245 MWwithdrawn2018-09PJM
Pennville - Adams 138 kVBatteries205 MWwithdrawn2021-09PJM
Pennville - Adams 138 kVSolar205 MWwithdrawn2023-02PJM
Pennville-Adams 138 kVSolar155 MWsuspended2019-02PJM
Keystone-Desoto 345 kVSolar150 MWactive2019-09PJM
Shelby 138 kVSolar150 MWwithdrawn2020-03PJM
AH2-114Solar150 MWwithdrawn2022-02PJM
Jay 138 kVBatteries150 MWwithdrawn2022-03PJM
Jay 138 kVSolar150 MWwithdrawn2023-03PJM
Jay 138 kVWind143 MWcompleted2020-05PJM
Jay 138 kVWind130 MWcompleted2017-03PJM
Pennville 138 kVSolar125 MWwithdrawn2021-06PJM
Pennville 138 kVBatteries125 MWwithdrawn2021-09PJM
Bluff Point 138kVWind120 MWcompleted2007-07PJM
Jay 138 kVSolar100 MWwithdrawn2020-04PJM

How Jay County compares

#812 in the US · #27 in IN

Jay County ranks #812 of 1,607 US counties by power waiting to connect, and #27 of 57 in Indiana.

CountyWaitingCapacity queued
Sullivan County206.4 GW
Pulaski County103.2 GW
Vermillion County42.4 GW
White County132.1 GW
Fountain County41.4 GW
Blackford County71.3 GW
St. Joseph County41.2 GW
Greene County61.2 GW

Common questions about power in Jay County

How long does it take to get power for a data center in Jay County, IN?

The median wait for a project still in the interconnection queue in Jay County is 6.2 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 4 projects in Jay County have reached energization and 19 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Jay County, IN?

289 MW is currently requested across 3 active interconnection requests, and 396 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Jay County, IN a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Indiana policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Jay County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.