3 interconnection applications are pending in Stanislaus County, CA, requesting 420 MW of new generating capacity, as of 15 August 2026. 3 projects have been built here and 20 have been withdrawn since 2004.
Source: interconnection queues published by CAISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Stanislaus County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Battery | 2 | 400 MW |
| Hybrid | 1 | 20 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 3 | 360 MW | 11.5% |
| Still pending | 3 | 420 MW | 11.5% |
| Withdrawn | 20 | 2.1 GW | 76.9% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Withdrawn project | Hybrid | 400 MW | withdrawn | 2021-04 | CAISO |
| GOLDEN FLATS | Battery | 300 MW | active | 2021-04 | CAISO |
| PROXIMA SOLAR | Hybrid | 300 MW | completed | 2016-05 | CAISO |
| Withdrawn project | Solar | 300 MW | withdrawn | 2015-04 | CAISO |
| Withdrawn project | Hybrid | 240 MW | withdrawn | 2019-04 | CAISO |
| Withdrawn project | Solar | 200 MW | withdrawn | 2018-04 | CAISO |
| Withdrawn project | Solar | 200 MW | withdrawn | 2018-04 | CAISO |
| Withdrawn project | Battery | 110 MW | withdrawn | 2021-04 | CAISO |
| Withdrawn project | Solar | 102 MW | withdrawn | 2016-05 | CAISO |
| Withdrawn project | Hybrid | 101 MW | withdrawn | 2017-05 | CAISO |
| OAKDALE STORAGE | Battery | 100 MW | active | 2021-04 | CAISO |
| Withdrawn project | Gas | 100 MW | withdrawn | 2004-11 | CAISO |
| Withdrawn project | Solar | 75 MW | withdrawn | 2011-03 | CAISO |
| Withdrawn project | Solar | 70 MW | withdrawn | 2011-03 | CAISO |
| Withdrawn project | Gas | 49 MW | withdrawn | 2008-04 | CAISO |
How this county ranks
Stanislaus County ranks #679 of 1,607 US counties by capacity currently queued, and #22 of 42 in California.
Other California counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Los Angeles County | 33 | 15.0 GW |
| Kern County | 51 | 13.8 GW |
| Riverside County | 23 | 8.4 GW |
| San Bernardino County | 19 | 7.3 GW |
| Imperial County | 35 | 6.7 GW |
| Fresno County | 28 | 6.5 GW |
| Sacramento County | 16 | 3.6 GW |
| Kings County | 8 | 2.5 GW |
Go deeper on Stanislaus County