The rules on data centers in Nevada

1 data center moratorium on file in Nevada, alongside 1 tracked policy event in the state. 4 large load interconnection requests are recorded here, totalling 289 MW. 1 interconnection deadlines bind projects in this state. As of 15 September 2026.

In plain words

Nevada has paused or restricted new data centers in at least one place. That is a decision by a government, not by us — the rulings are listed below with links. Meanwhile 4 big new power users have asked to connect here. See where they are in Nevada, or check your own address.

Decisions on file
1
bans, new charges, siting rules
Big new power users
4
289 MW
Counties involved
15
with power on the waiting list
Who runs the grid here
CAISO, LADWP, N-C, NVE, WAPA-DSW
read from county coverage

Every decision on file for Nevada

1 tracked
DateLevelWhat happenedCategoryStatus
localReno, NV extends data-center moratorium into 2027
Extension of existing pause in a major growth market. source
moratoriumin-effect

Key dates for projects here

1 dated · next closes 2026-10-15 (CAISO)
QueueWhat closesClosesStanding
CAISOCAISO Cluster 16 interconnection request window
Interconnection requests submitted through the GRIP portal.
2026-10-15confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

Federal decisions, which apply everywhere

6 items
DateWhat happenedStatus
2026-08-12DOE cancels all three remaining proposed NIETC transmission corridors
Lake Erie–Canada, Southwestern Grid Connector, and Tribal Energy Access corridors cancelled; the federal corridor-designation framework is dead. State siting is now the whole game. source
final
2026-06-18FERC §206 show-cause orders to all six RTOs on large-load integration (EL26-67 through EL26-72)
Every RTO/ISO must justify or reform its large-load interconnection rules. PJM (EL26-67) responses due 2026-08-17; comments due 2026-09-16. Compliance filings will become a primary structured source of load-queue transparency. source
open
2026-03-01FERC further guidance on co-located load interconnection (EL25-49 line of cases)
Follow-on to the Talen–Susquehanna ISA rejection (ER24-2172) and the PJM co-location show-cause; sets the frame for behind-the-meter data centers at generators. source
open
2026-02-12EIA-860S emergency-approved: state air-permit inventory of >1 MW backup generators
New collection motivated by AI data centers; backup-genset permits are the best forthcoming government proxy for data-center locations. EIA also running voluntary DC pilot surveys in TX, WA, NoVA. source
in-effect
2025-10-23FERC opens RM26-4: Interconnection of Large Loads to the Interstate Transmission System
DOE §403 directive forced an expedited rulemaking on large-load interconnection (large load defined >20 MW). ANOPR concepts: 60-day studies, cost allocation, co-location reliability rules. source
open
2024-05-13Order 2023/2023-A generator interconnection reform — cluster transitions ongoing
All ISOs moved to cluster studies with readiness deposits; PJM transition cycles TC1/TC2, ISO-NE first cluster 2026, CAISO Cluster 15. Reshapes every queue metric on this dashboard. source
implementing

Big new power users recorded in Nevada

4 requests

Requests to connect large new customers — data centers, factories, electrification — rather than power plants. Nobody is required to publish these, so what exists publicly is thin: this is what we hold, not what exists.

RequestCountyCapacityStatusQueueStated use
Lithium NevadaHumboldt County143 MWenergizedBPAnot stated
Denio Junction 139 MWHumboldt County139 MWactiveBPAnot stated
Long CanyonWest Wendover7 MWwithdrawnBPAnot stated
West WendoverWest Wendover0 MWactiveBPAnot stated

Most of these filings do not say what the power is for. “Not stated” is the filing's own silence — these rows must not be described as data centers.

Which counties in Nevada this is happening in

top 10 by power requested
CountyWaiting to connectCapacity queued
Clark County5715.5 GW
Nye County134.9 GW
Churchill County154.1 GW
Humbolt123.0 GW
Story73.0 GW
Lyon County112.9 GW
Washoe County122.9 GW
Esmerelda92.7 GW
White Pine County51.8 GW
Lincoln County21.2 GW

Before you commit to a site in Nevada

A county report puts the policy position, the queue and the deadlines for one county in a sourced PDF, with the date each figure was true on every page. The first one is free.

Get a free county report Nevada interconnection queue The deadline calendar