Data centers and new power in Esmerelda, NV

2.7 GW of new power is waiting to connect to the grid in Esmerelda, NV — 9 active requests. Typical wait: 3.8 years. 0 projects are built, 20 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Esmerelda itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Esmerelda

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Esmerelda right now.

2.7 GW
of new power is waiting to connect
9 projects asked. Not yet approved. Roughly what 2.1 million homes use.
0 MW
has actually been built
0 projects switched on so far.
3.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 31%
  • Withdrawn 69%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Esmerelda.

What kind of power is asking to connect

  • Solar 96%
  • Geothermal 4%

By capacity requested. Data as of 14 October 2026.

All the numbers

29 requests ever filed
Pending applications
9
of 29 ever filed
Capacity queued
2.7 GW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
20 withdrawn
Median wait
3.8 yr
for applications still pending

Source: interconnection queues published by NVE. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting92.7 GW31.0%
Withdrawn2010.0 GW69.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar62.6 GW
Geothermal397 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Company PMSolar1.5 GWwithdrawn2023-03NVE
25-00394Solar1.0 GWactive2025-07NVE
Company OZSolar1.0 GWwithdrawn2023-01NVE
Company PBSolar1.0 GWwithdrawn2023-01NVE
Company QIWind960 MWwithdrawn2023-09NVE
Company OLSolar500 MWwithdrawn2023-01NVE
Company OMSolar500 MWwithdrawn2023-01NVE
Company ONSolar500 MWwithdrawn2023-01NVE
Company OOBatteries500 MWwithdrawn2023-01NVE
Company PASolar500 MWwithdrawn2023-01NVE
Company PKSolar500 MWactive2022-03NVE
Company PSSolar500 MWwithdrawn2023-03NVE
Company PTSolar500 MWwithdrawn2023-03NVE
Company PXSolar500 MWwithdrawn2023-03NVE
Withdrawn projectGeothermal427 MWwithdrawn2021-04CAISO

How Esmerelda compares

#130 in the US · #8 in NV

Esmerelda ranks #130 of 1,607 US counties by power waiting to connect, and #8 of 15 in Nevada.

CountyWaitingCapacity queued
Clark County5715.5 GW
Nye County134.9 GW
Churchill County154.1 GW
Humbolt123.0 GW
Story73.0 GW
Lyon County112.9 GW
Washoe County122.9 GW
White Pine County51.8 GW

Common questions about power in Esmerelda

How long does it take to get power for a data center in Esmerelda, NV?

The median wait for a project still in the interconnection queue in Esmerelda is 3.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Esmerelda have reached energization and 20 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Esmerelda, NV?

2.7 GW is currently requested across 9 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Esmerelda, NV a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Nevada policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Esmerelda — NVE — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Esmerelda

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Esmerelda on the map County reports All of Nevada