Data centers and new power in Iowa

15.4 GW of new power is waiting to connect to the grid in Iowa — 80 requests across 21 counties. That is the 33rd largest amount of any state. 44 projects are built, 135 withdrawn. Data as of 14 October 2026.

The power picture

What is happening with electricity in Iowa

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Iowa right now.

15.4 GW
of new power is waiting to connect
80 projects asked. Not yet approved. Roughly what 12.3 million homes use.
5.2 GW
has actually been built
44 projects switched on so far.
135
projects gave up
Withdrawn before being built. Normal nationally.

Where every request ever filed here ended up

  • Built 17%
  • Still waiting 31%
  • Withdrawn 52%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Iowa.

What kind of power is asking to connect

  • Solar 37%
  • Wind 34%
  • Natural gas 17%
  • Nuclear 8%
  • Solar + battery 3%

By capacity requested. Data as of 14 October 2026.

All the numbers

259 requests ever filed
Waiting to connect
80
of 259 ever filed
Capacity requested
15.4 GW
asked for, not approved
Already built
5.2 GW
44 switched on
Built vs decided
24.6%
135 withdrawn
Counties involved
21
with five or more requests
Big new power users
none recorded
0 requests

Source: the interconnection queues of every transmission provider operating in Iowa. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar355.8 GW
Wind255.2 GW
Natural gas132.6 GW
Nuclear51.3 GW
Solar + battery2513 MW

Who runs the waiting list in Iowa

Grid operator or utilityRequestsCapacity pending
MISO22915.1 GW
SPP8285 MW
WAPA-IS200 MW
PJM20 MW

Counties in Iowa

21 with power on the waiting list

Every county with at least five requests on file. Open one to check an address, or see the schools near any mapped data center.

CountyWaitingCapacity queuedAlready built
Linn County102.3 GW295 MW
Cerro Gordo County51.4 GW0 MW
Washington County31.1 GW0 MW
Marshall County4717 MW0 MW
Clinton County3610 MW600 MW
Franklin County3560 MW0 MW
Story County3550 MW0 MW
Webster County2470 MW0 MW
Muscatine County3329 MW250 MW
Dubuque County2260 MW0 MW
Worth County1230 MW545 MW
Palo Alto County1200 MW450 MW
Pottawattamie County1200 MW0 MW
Pocahontas County1156 MW7 MW
Howard County1155 MW220 MW
Tama County1100 MW169 MW
Clay County00 MW45 MW
Crawford County00 MW6 MW
Des Moines County00 MW50 MW
Hancock County00 MW0 MW
Mills County00 MW50 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

Data center campuses recorded in Iowa

4 listed
CampusOperatorReported demand
Google Council Bluffs (East)Google237 MW
Microsoft Project OsmiumMicrosoft190 MW
Google Cedar RapidsGoogle0 MW
QTS Cedar Rapids0 MW

Tagged as a data center by our classification, not by the operator’s own statement. Only campuses with coordinates can be mapped.