Data centers and new power in Muscatine County, IA

329 MW of new power is waiting to connect to the grid in Muscatine County, IA — 3 active requests. Typical wait: 4.1 years. 2 projects are built, 0 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Muscatine County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Muscatine County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Muscatine County right now.

329 MW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 264,000 homes use.
250 MW
has actually been built
2 projects switched on so far.
4.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 40%
  • Still waiting 60%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Muscatine County.

What kind of power is asking to connect

  • Solar 54%
  • Wind 46%

By capacity requested. Data as of 14 October 2026.

All the numbers

5 requests ever filed
Pending applications
3
of 5 ever filed
Capacity queued
329 MW
requested, not committed
Already built
250 MW
2 projects connected
Built vs decided
100.0%
0 withdrawn
Median wait
4.1 yr
for applications still pending
Connected capacity
300 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built2250 MW40.0%
Still waiting3329 MW60.0%
Withdrawn00 MW0.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar2179 MW
Wind1150 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 5 by size
ProjectTypeCapacityStatusFiledQueue
Sub 92 345 kVSolar200 MWcompleted2019-04MISO
SUB 56 - SUB 89 161.0kVSolar156 MWactive2024-04MISO
Walcott 345 kVWind150 MWactive2022-09MISO
Sub 92 345 kV SubstationSolar50 MWcompleted2019-04MISO
Grandview Substation 69 kVSolar23 MWactive2021-12MISO

How Muscatine County compares

#750 in the US · #9 in IA

Muscatine County ranks #750 of 1,607 US counties by power waiting to connect, and #9 of 21 in Iowa.

CountyWaitingCapacity queued
Linn County102.3 GW
Cerro Gordo County51.4 GW
Washington County31.1 GW
Marshall County4717 MW
Clinton County3610 MW
Franklin County3560 MW
Story County3550 MW
Webster County2470 MW

Common questions about power in Muscatine County

How long does it take to get power for a data center in Muscatine County, IA?

The median wait for a project still in the interconnection queue in Muscatine County is 4.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 2 projects in Muscatine County have reached energization and 0 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Muscatine County, IA?

329 MW is currently requested across 3 active interconnection requests, and 250 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Muscatine County, IA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Iowa policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Muscatine County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.