Data centers and new power in Dubuque County, IA

260 MW of new power is waiting to connect to the grid in Dubuque County, IA — 2 active requests. Typical wait: 4.1 years. 0 projects are built, 3 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Dubuque County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Dubuque County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Dubuque County right now.

260 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 208,000 homes use.
0 MW
has actually been built
0 projects switched on so far.
4.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 40%
  • Withdrawn 60%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Dubuque County.

What kind of power is asking to connect

  • Natural gas 62%
  • Solar 38%

By capacity requested. Data as of 14 October 2026.

All the numbers

5 requests ever filed
Pending applications
2
of 5 ever filed
Capacity queued
260 MW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
3 withdrawn
Median wait
4.1 yr
for applications still pending
Connected capacity
27 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting2260 MW40.0%
Withdrawn3350 MW60.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Natural gas1160 MW
Solar1100 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 5 by size
ProjectTypeCapacityStatusFiledQueue
Salem - Hickory Creek 345 kV lineNatural gas160 MWactive2022-09MISO
Salem 345kV SubstationSolar150 MWwithdrawn2018-03MISO
Center Grove 161kV SubstationSolar100 MWwithdrawn2019-04MISO
Gardner 69 kV substationSolar100 MWactive2022-09MISO
Salem 161kvSolar100 MWwithdrawn2024-04MISO

How Dubuque County compares

#828 in the US · #10 in IA

Dubuque County ranks #828 of 1,607 US counties by power waiting to connect, and #10 of 21 in Iowa.

CountyWaitingCapacity queued
Linn County102.3 GW
Cerro Gordo County51.4 GW
Washington County31.1 GW
Marshall County4717 MW
Clinton County3610 MW
Franklin County3560 MW
Story County3550 MW
Webster County2470 MW

Common questions about power in Dubuque County

How long does it take to get power for a data center in Dubuque County, IA?

The median wait for a project still in the interconnection queue in Dubuque County is 4.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Dubuque County have reached energization and 3 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Dubuque County, IA?

260 MW is currently requested across 2 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Dubuque County, IA a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Iowa policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Dubuque County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Dubuque County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Dubuque County on the map County reports All of Iowa