Duke interconnection queue

289 interconnection requests are active in Duke, totalling 30.0 GW, as of 15 August 2026. Of the 1,067 requests ever filed here, 90 were built and 674 were withdrawn — a build rate of 11.8% on decided applications.

Active requests
289
of 1,067 ever filed
Capacity queued
30.0 GW
requested, not committed
Built vs decided
11.8%
90 built, 674 withdrawn
Median wait so far
2.1 yr
for requests still active
Median time to build
3.5 yr
request to commercial operation

Source: the Duke interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.

What is queued in Duke, by fuel

FuelProjectsCapacity requested
Gas6613.6 GW
Solar1367.6 GW
Battery415.2 GW
Other303.3 GW
Hydro9148 MW
Nuclear5139 MW
Coal260 MW

Where Duke’s queue sits

StateApplicationsCapacity pending
North Carolina40918.8 GW
South Carolina2796.2 GW
Florida3665.1 GW

Largest active requests

ProjectFuelCapacityCountyStateFiled
977726Gas1.6 GWRowan CountyNC2025-06
958347Gas1.5 GWPerson CountyNC2024-06
957264Gas1.4 GWAnderson CountySC2024-06
977731Gas1.4 GWDavidson CountyNC2025-06
977454Gas990 MWAnson CountyNC2025-06
977564Gas810 MWCleveland CountyNC2025-06
137Gas575 MWPasco CountyFL2015-11
4Gas537 MWOsceola CountyFL1999-04
977444Gas495 MWAnson CountyNC2025-06
956747Gas455 MWRowanSC2024-06
960889Gas455 MWRowan CountyNC2024-06
961188Gas455 MWStokes CountyNC2024-06
961210Gas455 MWStokes CountyNC2024-06
899771Gas313 MWPerson CountyNC2023-06
977298Other300 MWWake CountyNC2025-06