CAISO interconnection queue
272 interconnection requests are active in CAISO, totalling 75.7 GW, as of 15 August 2026. Of the 2,285 requests ever filed here, 251 were built and 1,762 were withdrawn — a build rate of 12.5% on decided applications.
Active requests
272
of 2,285 ever filed
Capacity queued
75.7 GW
requested, not committed
Built vs decided
12.5%
251 built, 1,762 withdrawn
Median wait so far
6.3 yr
for requests still active
Median time to build
6.2 yr
request to commercial operation
Source: the CAISO interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.
What is queued in CAISO, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Hybrid | 155 | 47.3 GW |
| Battery | 90 | 24.2 GW |
| Wind | 10 | 2.7 GW |
| Solar | 6 | 1.3 GW |
| Gas | 2 | 55 MW |
| Geothermal | 1 | 53 MW |
| Other | 1 | 44 MW |
| Hydro | 2 | 5 MW |
| Unknown | 5 | — |
Where CAISO’s queue sits
| State | Applications | Capacity pending |
|---|---|---|
| California | 2,076 | 59.6 GW |
| Arizona | 72 | 7.4 GW |
| Nevada | 104 | 7.4 GW |
| MX | 18 | 1.3 GW |
| Idaho | 2 | 0 MW |
| New Mexico | 1 | 0 MW |
| Wyoming | 1 | 0 MW |
Largest active requests
| Project | Fuel | Capacity | County | State | Filed |
|---|---|---|---|---|---|
| ATLAS COMPLEX | Hybrid | 3.2 GW | La Paz County | AZ | 2017-05 |
| HOLMAN | Hybrid | 1.5 GW | Monterey County | CA | 2021-04 |
| SANBORN HYBRID 3 | Hybrid | 1.4 GW | Kern County | CA | 2019-04 |
| ANGELENO SOLAR FARM | Hybrid | 1.1 GW | Los Angeles County | CA | 2019-04 |
| WINGTIP SOLAR 1 | Hybrid | 1.1 GW | Merced County | CA | 2021-04 |
| DARDEN | Hybrid | 1.1 GW | Fresno County | CA | 2021-04 |
| UMBRIEL | Hybrid | 1.1 GW | Imperial County | CA | 2021-04 |
| WINDWALKER OFFSHORE | Wind | 1.0 GW | San Luis Obispo County | CA | 2020-04 |
| PLUM | Hybrid | 1.0 GW | Kings County | CA | 2021-04 |
| BOUSE SOLAR AND STORAGE PLANT | Hybrid | 1.0 GW | La Paz County | AZ | 2021-04 |
| VIENTO FRONTERIZO | Wind | 973 MW | MUNICIPALITY OF TECATE | MX | 2020-04 |
| BUTTONBUSH SOLAR HYBRID ENERGY CENTER | Hybrid | 800 MW | Kern County | CA | 2019-04 |
| IRVING STORAGE | Battery | 750 MW | Monterey County | CA | 2019-05 |
| ARIDA 2 SOLAR FARM | Hybrid | 700 MW | Clark County | NV | 2019-04 |
| MENIFEE POWER BANK | Battery | 680 MW | Riverside County | CA | 2019-04 |