Data centers and new power in Converse County, WY

2.3 GW of new power is waiting to connect to the grid in Converse County, WY — 10 active requests. Typical wait: 3.1 years. 7 projects are built, 28 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Converse County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Converse County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Converse County right now.

2.3 GW
of new power is waiting to connect
10 projects asked. Not yet approved. Roughly what 1.8 million homes use.
1.5 GW
has actually been built
7 projects switched on so far.
3.1 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 15%
  • Still waiting 22%
  • Withdrawn 61%
  • Paused 2%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Converse County.

What kind of power is asking to connect

  • Batteries 33%
  • Solar 30%
  • Natural gas 26%
  • Wind 10%

By capacity requested. Data as of 14 October 2026.

All the numbers

46 requests ever filed
Pending applications
10
of 46 ever filed
Capacity queued
2.3 GW
requested, not committed
Already built
1.5 GW
7 projects connected
Built vs decided
20.0%
28 withdrawn
Median wait
3.1 yr
for applications still pending
Connected capacity
2.4 GW
indicator, see note

Source: interconnection queues published by CLPT, PacifiCorp. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built71.5 GW15.2%
Still waiting102.3 GW21.7%
Withdrawn287.0 GW60.9%
Paused1—2.2%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Batteries3750 MW
Solar3691 MW
Natural gas1600 MW
Wind3234 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
137Wind1.0 GWwithdrawn2007-05PacifiCorp
T2-017Natural gas600 MWactive2025-08PacifiCorp
712Wind520 MWcompleted2015-10PacifiCorp
135Wind500 MWwithdrawn2007-05PacifiCorp
136Wind500 MWwithdrawn2007-05PacifiCorp
50Natural gas500 MWwithdrawn2005-01PacifiCorp
C2-17Solar500 MWwithdrawn2022-04PacifiCorp
C2-23Solar500 MWwithdrawn2022-04PacifiCorp
C3-066Solar500 MWwithdrawn2023-05PacifiCorp
713Wind350 MWcompleted2015-10PacifiCorp
S0026Batteries350 MWactive2024-02PacifiCorp
S0028Batteries320 MWactive2024-02PacifiCorp
CLPT G26Wind300 MWwithdrawn2023-04CLPT
CLPT G28Wind300 MWwithdrawn2024-01CLPT
1171Solar300 MWwithdrawn2019-10PacifiCorp

How Converse County compares

#162 in the US · #4 in WY

Converse County ranks #162 of 1,607 US counties by power waiting to connect, and #4 of 12 in Wyoming.

CountyWaitingCapacity queued
Laramie County225.4 GW
Platte County123.4 GW
Carbon/Albany162.7 GW
Lincoln County51.8 GW
Sweetwater County21.2 GW
Albany County5964 MW
Campbell County3590 MW
Natrona County4409 MW

Common questions about power in Converse County

How long does it take to get power for a data center in Converse County, WY?

The median wait for a project still in the interconnection queue in Converse County is 3.1 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 7 projects in Converse County have reached energization and 28 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Converse County, WY?

2.3 GW is currently requested across 10 active interconnection requests, and 1.5 GW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Converse County, WY a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Wyoming policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Converse County — CLPT, PacifiCorp — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.