Albany County, WY interconnection queue
5 interconnection applications are pending in Albany County, WY, requesting 964 MW of new generating capacity, as of 15 August 2026. 1 projects have been built here and 17 have been withdrawn since 2007.
Source: interconnection queues published by PacifiCorp, SPP. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Albany County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Wind | 2 | 504 MW |
| Solar | 2 | 310 MW |
| Hybrid | 1 | 150 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 1 | 320 MW | 4.2% |
| Still pending | 5 | 964 MW | 20.8% |
| Withdrawn | 17 | 3.6 GW | 70.8% |
| Suspended | 1 | — | 4.2% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| 920 | Wind | 630 MW | withdrawn | 2017-08 | PacifiCorp |
| 298 | Wind | 400 MW | withdrawn | 2009-10 | PacifiCorp |
| 132 | Wind | 361 MW | withdrawn | 2007-05 | PacifiCorp |
| 409 | Wind | 320 MW | completed | 2012-01 | PacifiCorp |
| 933 | Solar | 300 MW | withdrawn | 2017-08 | PacifiCorp |
| 934 | Wind | 300 MW | withdrawn | 2017-08 | PacifiCorp |
| 935 | Wind | 300 MW | withdrawn | 2017-08 | PacifiCorp |
| 936 | Solar | 300 MW | withdrawn | 2017-08 | PacifiCorp |
| 719 | Wind | 280 MW | suspended | 2015-11 | PacifiCorp |
| 2019-G2 | Wind | 252 MW | active | 2018-11 | SPP |
| 2019-G1 | Wind | 252 MW | active | 2018-11 | SPP |
| C1-53 | Wind | 190 MW | withdrawn | 2021-05 | PacifiCorp |
| 1107 | Solar | 160 MW | withdrawn | 2019-01 | PacifiCorp |
| C4-109 | Solar | 160 MW | withdrawn | 2024-05 | PacifiCorp |
| T2-026 | Solar | 160 MW | active | 2025-09 | PacifiCorp |
How this county ranks
Albany County ranks #385 of 1,607 US counties by capacity currently queued, and #7 of 12 in Wyoming.
Other Wyoming counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Laramie County | 22 | 5.4 GW |
| Platte County | 12 | 3.4 GW |
| Carbon/Albany | 16 | 2.7 GW |
| Converse County | 11 | 2.5 GW |
| Lincoln County | 5 | 1.8 GW |
| Sweetwater County | 2 | 1.2 GW |
| Campbell County | 3 | 590 MW |
| Natrona County | 4 | 409 MW |
Go deeper on Albany County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.