Data centers and new power in St. Croix County, WI
0 MW of new power is waiting to connect to the grid in St. Croix County, WI — 0 active requests. 1 projects are built, 5 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside St. Croix County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in St. Croix County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in St. Croix County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for St. Croix County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
6 requests ever filed
Source: interconnection queues published by the transmission providers serving this county. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 1 | 100 MW | 16.7% |
| Still waiting | 0 | 0 MW | 0.0% |
| Withdrawn | 5 | 525 MW | 83.3% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
Key dates for projects here
no dated windows published
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 6 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Pine Lake to Three Lakes 115 kV | Solar | 160 MW | withdrawn | 2022-02 | MISO |
| Pine Lake Tap - APPLE RIVER (DPC) 161.0kV | Solar | 150 MW | withdrawn | 2024-04 | MISO |
| Pine Lake 161 kV Substation | Solar | 115 MW | withdrawn | 2022-09 | MISO |
| Pine Lake to Apple River 161 kV | Solar | 100 MW | completed | 2020-06 | MISO |
| Three Lakes - Pine Lake 115 kV | Solar | 100 MW | withdrawn | 2021-10 | MISO |
| PINE LAKE TO THREE LAKES 115 KV | Solar | 0 MW | withdrawn | 2022-02 | MISO |
How St. Croix County compares
#1606 in the US · #18 in WI
St. Croix County ranks #1606 of 1,607 US counties by power waiting to connect, and #18 of 18 in Wisconsin.
| County | Waiting | Capacity queued |
|---|---|---|
| Kenosha County | 6 | 1.9 GW |
| Portage County | 6 | 1.7 GW |
| Walworth County | 4 | 1.6 GW |
| Dane County | 3 | 1.3 GW |
| Columbia County | 6 | 1.3 GW |
| Fond du Lac County | 2 | 625 MW |
| Rock County | 5 | 510 MW |
| Waushara County | 4 | 330 MW |
Common questions about power in St. Croix County
How long does it take to get power for a data center in St. Croix County, WI?
We do not yet have a median wait for St. Croix County. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in St. Croix County have reached energization and 5 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in St. Croix County, WI?
0 MW is currently requested across 0 active interconnection requests, and 100 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is St. Croix County, WI a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Wisconsin policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving St. Croix County — the utilities in this area — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.