Data centers and new power in Walworth County, WI

1.6 GW of new power is waiting to connect to the grid in Walworth County, WI — 4 active requests. Typical wait: 1.3 years. 0 projects are built, 8 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Walworth County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Walworth County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Walworth County right now.

1.6 GW
of new power is waiting to connect
4 projects asked. Not yet approved. Roughly what 1.3 million homes use.
0 MW
has actually been built
0 projects switched on so far.
1.3 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 33%
  • Withdrawn 67%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Walworth County.

What kind of power is asking to connect

  • Natural gas 94%
  • Solar 6%

By capacity requested. Data as of 14 October 2026.

All the numbers

12 requests ever filed
Pending applications
4
of 12 ever filed
Capacity queued
1.6 GW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
8 withdrawn
Median wait
1.3 yr
for applications still pending
Connected capacity
26 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting41.6 GW33.3%
Withdrawn81.0 GW66.7%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Natural gas31.5 GW
Solar1100 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 12 by size
ProjectTypeCapacityStatusFiledQueue
Sugar Creek 345 kVNatural gas950 MWactive2025-10MISO
North Creek 138kVNatural gas324 MWactive2025-05MISO
North Creek 138kV StationNatural gas250 MWactive2025-09MISO
North Lake Geneva - Sugar Creek - Burlington 138kV Line TapSolar200 MWwithdrawn2018-03MISO
North Lake Geneva 138kV SubstationSolar200 MWwithdrawn2018-03MISO
North Lake Geneva - Sugar Creek - Burlington 138kV Line TapSolar200 MWwithdrawn2018-03MISO
University - Mukwanago UNIG52 Line TapSolar124 MWwithdrawn2017-06MISO
SW Delavan 138kVSolar100 MWwithdrawn2021-08MISO
University to Mukwanago 138kV LineSolar100 MWwithdrawn2020-06MISO
Brick Church 138 kVSolar100 MWactive2024-01MISO
Bluff Creek (Tap) to Sugar Creek 138 kV line tapSolar75 MWwithdrawn2017-06MISO
SW Delavan 138kVSolar35 MWwithdrawn2021-08MISO

How Walworth County compares

#235 in the US · #3 in WI

Walworth County ranks #235 of 1,607 US counties by power waiting to connect, and #3 of 18 in Wisconsin.

CountyWaitingCapacity queued
Kenosha County61.9 GW
Portage County61.7 GW
Dane County31.3 GW
Columbia County61.3 GW
Fond du Lac County2625 MW
Rock County5510 MW
Waushara County4330 MW
Barron County3295 MW

Common questions about power in Walworth County

How long does it take to get power for a data center in Walworth County, WI?

The median wait for a project still in the interconnection queue in Walworth County is 1.3 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Walworth County have reached energization and 8 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Walworth County, WI?

1.6 GW is currently requested across 4 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Walworth County, WI a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Wisconsin policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Walworth County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Walworth County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Walworth County on the map County reports All of Wisconsin