Data centers and new power in Woodward County, OK

916 MW of new power is waiting to connect to the grid in Woodward County, OK — 5 active requests. Typical wait: 4.3 years. 4 projects are built, 27 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Woodward County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Woodward County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Woodward County right now.

916 MW
of new power is waiting to connect
5 projects asked. Not yet approved. Roughly what 733,000 homes use.
503 MW
has actually been built
4 projects switched on so far.
4.3 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 11%
  • Still waiting 14%
  • Withdrawn 75%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Woodward County.

What kind of power is asking to connect

  • Solar 59%
  • Wind 41%

By capacity requested. Data as of 14 October 2026.

All the numbers

36 requests ever filed
Pending applications
5
of 36 ever filed
Capacity queued
916 MW
requested, not committed
Already built
503 MW
4 projects connected
Built vs decided
12.9%
27 withdrawn
Median wait
4.3 yr
for applications still pending
Connected capacity
1.0 GW
indicator, see note

Source: interconnection queues published by SPP. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built4503 MW11.1%
Still waiting5916 MW13.9%
Withdrawn274.6 GW75.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar3538 MW
Wind2378 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
GEN-2010-043Natural gas320 MWwithdrawn2010-09SPP
GEN-2012-016Natural gas312 MWwithdrawn2012-08SPP
GEN-2008-045Wind300 MWwithdrawn2008-05SPP
GEN-2024-075Solar300 MWwithdrawn2024-10SPP
GEN-2024-313Solar300 MWwithdrawn2025-03SPP
GEN-2022-016Solar288 MWactive2022-06SPP
GEN-2008-086Wind250 MWwithdrawn2008-08SPP
GEN-2022-048Wind250 MWwithdrawn2022-06SPP
GEN-2002-010Wind240 MWwithdrawn2002-07SPP
GEN-2021-028Solar204 MWwithdrawn2021-05SPP
GEN-2021-025Wind203 MWactive2021-05SPP
GEN-2007-051Wind200 MWwithdrawn2007-11SPP
GEN-2008-115Wind200 MWwithdrawn2008-09SPP
GEN-2015-086Wind200 MWwithdrawn2015-09SPP
GEN-2024-314Solar199 MWwithdrawn2025-03SPP

How Woodward County compares

#408 in the US · #10 in OK

Woodward County ranks #408 of 1,607 US counties by power waiting to connect, and #10 of 50 in Oklahoma.

CountyWaitingCapacity queued
Oklahoma County133.0 GW
Texas County112.1 GW
Creek County32.0 GW
Payne County61.8 GW
Johnston County71.5 GW
Muskogee County61.4 GW
Mayes County91.3 GW
Grady County71.3 GW

Common questions about power in Woodward County

How long does it take to get power for a data center in Woodward County, OK?

The median wait for a project still in the interconnection queue in Woodward County is 4.3 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 4 projects in Woodward County have reached energization and 27 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Woodward County, OK?

916 MW is currently requested across 5 active interconnection requests, and 503 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Woodward County, OK a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Oklahoma policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Woodward County — SPP — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.