Data centers and new power in Texas County, OK

2.1 GW of new power is waiting to connect to the grid in Texas County, OK — 11 active requests. Typical wait: 9.9 years. 1 projects are built, 18 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Texas County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Texas County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Texas County right now.

2.1 GW
of new power is waiting to connect
11 projects asked. Not yet approved. Roughly what 1.7 million homes use.
200 MW
has actually been built
1 projects switched on so far.
9.9 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 3%
  • Still waiting 37%
  • Withdrawn 60%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Texas County.

What kind of power is asking to connect

  • Wind 90%
  • Solar 5%
  • Solar + battery 5%

By capacity requested. Data as of 14 October 2026.

All the numbers

30 requests ever filed
Pending applications
11
of 30 ever filed
Capacity queued
2.1 GW
requested, not committed
Already built
200 MW
1 projects connected
Built vs decided
5.3%
18 withdrawn
Median wait
9.9 yr
for applications still pending
Connected capacity
201 MW
indicator, see note

Source: interconnection queues published by SPP. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built1200 MW3.3%
Still waiting112.1 GW36.7%
Withdrawn184.3 GW60.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Wind91.9 GW
Solar1103 MW
Solar + battery1100 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
GEN-2024-127Natural gas1.3 GWwithdrawn2025-03SPP
GEN-2007-041Wind600 MWwithdrawn2007-09SPP
GEN-2008-028Wind360 MWwithdrawn2008-04SPP
GEN-2016-142Wind350 MWactive2016-11SPP
GEN-2016-141Wind350 MWactive2016-11SPP
GEN-2008-110Wind299 MWwithdrawn2008-09SPP
GEN-2007-046Wind200 MWcompleted2007-10SPP
GEN-2014-037Wind200 MWwithdrawn2014-09SPP
GEN-2022-157Solar200 MWwithdrawn2023-02SPP
GEN-2016-138Wind188 MWactive2016-11SPP
GEN-2016-137Wind188 MWactive2016-11SPP
GEN-2016-134Wind188 MWactive2016-11SPP
GEN-2016-133Wind188 MWactive2016-11SPP
GEN-2016-146Wind175 MWactive2016-11SPP
GEN-2016-145Wind175 MWactive2016-11SPP

How Texas County compares

#179 in the US · #2 in OK

Texas County ranks #179 of 1,607 US counties by power waiting to connect, and #2 of 50 in Oklahoma.

CountyWaitingCapacity queued
Oklahoma County133.0 GW
Creek County32.0 GW
Payne County61.8 GW
Johnston County71.5 GW
Muskogee County61.4 GW
Mayes County91.3 GW
Grady County71.3 GW
Canadian County71.2 GW

Common questions about power in Texas County

How long does it take to get power for a data center in Texas County, OK?

The median wait for a project still in the interconnection queue in Texas County is 9.9 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Texas County have reached energization and 18 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Texas County, OK?

2.1 GW is currently requested across 11 active interconnection requests, and 200 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Texas County, OK a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Oklahoma policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Texas County — SPP — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.