Data centers and new power in Grady County, OK

1.3 GW of new power is waiting to connect to the grid in Grady County, OK — 7 active requests. Typical wait: 4.3 years. 8 projects are built, 9 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Grady County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Grady County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Grady County right now.

1.3 GW
of new power is waiting to connect
7 projects asked. Not yet approved. Roughly what 1 million homes use.
851 MW
has actually been built
8 projects switched on so far.
4.3 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 33%
  • Still waiting 29%
  • Withdrawn 38%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Grady County.

What kind of power is asking to connect

  • Solar 74%
  • Wind 17%
  • Solar + battery 9%

By capacity requested. Data as of 14 October 2026.

All the numbers

24 requests ever filed
Pending applications
7
of 24 ever filed
Capacity queued
1.3 GW
requested, not committed
Already built
851 MW
8 projects connected
Built vs decided
47.1%
9 withdrawn
Median wait
4.3 yr
for applications still pending
Connected capacity
486 MW
indicator, see note

Source: interconnection queues published by SPP. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built8851 MW33.3%
Still waiting71.3 GW29.2%
Withdrawn91.7 GW37.5%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar5942 MW
Wind1215 MW
Solar + battery1120 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
GEN-2001-025Natural gas580 MWwithdrawn2001-07SPP
GEN-2018-055Solar252 MWactive2018-05SPP
GEN-2017-150Solar250 MWactive2017-11SPP
GEN-2013-037Wind250 MWwithdrawn2013-12SPP
GEN-2015-092Wind250 MWwithdrawn2015-09SPP
GEN-2014-057Wind250 MWcompleted2014-09SPP
GEN-2017-233Wind215 MWactive2017-11SPP
GEN-2023-035Solar200 MWactive2023-10SPP
GEN-2022-055Solar200 MWactive2022-06SPP
GEN-2007-043Wind200 MWcompleted2007-10SPP
GEN-2011-029Wind200 MWwithdrawn2011-03SPP
GEN-2024-172Batteries190 MWwithdrawn2025-03SPP
GEN-2024-362Solar + battery120 MWactive2025-03SPP
GEN-2011-050Wind108 MWcompleted2011-09SPP
GEN-2009-034Wind102 MWwithdrawn2009-08SPP

How Grady County compares

#299 in the US · #8 in OK

Grady County ranks #299 of 1,607 US counties by power waiting to connect, and #8 of 50 in Oklahoma.

CountyWaitingCapacity queued
Oklahoma County133.0 GW
Texas County112.1 GW
Creek County32.0 GW
Payne County61.8 GW
Johnston County71.5 GW
Muskogee County61.4 GW
Mayes County91.3 GW
Canadian County71.2 GW

Common questions about power in Grady County

How long does it take to get power for a data center in Grady County, OK?

The median wait for a project still in the interconnection queue in Grady County is 4.3 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 8 projects in Grady County have reached energization and 9 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Grady County, OK?

1.3 GW is currently requested across 7 active interconnection requests, and 851 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Grady County, OK a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Oklahoma policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Grady County — SPP — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Grady County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Grady County on the map County reports All of Oklahoma