Data centers and new power in Columbus County, NC

102 MW of new power is waiting to connect to the grid in Columbus County, NC — 2 active requests. Typical wait: 1.3 years. 0 projects are built, 7 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Columbus County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Columbus County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Columbus County right now.

102 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 82,000 homes use.
0 MW
has actually been built
0 projects switched on so far.
1.3 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 22%
  • Withdrawn 78%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Columbus County.

What kind of power is asking to connect

  • Solar 78%
  • Other 22%

By capacity requested. Data as of 14 October 2026.

All the numbers

9 requests ever filed
Pending applications
2
of 9 ever filed
Capacity queued
102 MW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
7 withdrawn
Median wait
1.3 yr
for applications still pending
Connected capacity
166 MW
indicator, see note

Source: interconnection queues published by Duke. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting2102 MW22.2%
Withdrawn71.0 GW77.8%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar180 MW
Other122 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 9 by size
ProjectTypeCapacityStatusFiledQueue
66858Solar700 MWwithdrawn2020-02Duke
977914Solar80 MWactive2025-06Duke
569188Solar75 MWwithdrawn2022-06Duke
890899Solar75 MWwithdrawn2023-06Duke
920645Solar75 MWwithdrawn2023-09Duke
566856Solar60 MWwithdrawn2022-06Duke
977788Other22 MWactive2025-06Duke
886387Other22 MWwithdrawn2023-06Duke
5037Solar2 MWwithdrawn2016-04Duke

How Columbus County compares

#1078 in the US · #31 in NC

Columbus County ranks #1078 of 1,607 US counties by power waiting to connect, and #31 of 44 in North Carolina.

CountyWaitingCapacity queued
Pinal County4610.6 GW
Person County41.9 GW
Washington County61.6 GW
Anson County31.5 GW
Davidson County21.5 GW
Wayne County231.3 GW
Stokes County31.2 GW
Richmond County7974 MW

Common questions about power in Columbus County

How long does it take to get power for a data center in Columbus County, NC?

The median wait for a project still in the interconnection queue in Columbus County is 1.3 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Columbus County have reached energization and 7 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Columbus County, NC?

102 MW is currently requested across 2 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Columbus County, NC a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our North Carolina policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Columbus County — Duke — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.