Data centers and new power in Richmond County, NC

974 MW of new power is waiting to connect to the grid in Richmond County, NC — 7 active requests. Typical wait: 1.5 years. 6 projects are built, 9 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Richmond County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Richmond County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Richmond County right now.

974 MW
of new power is waiting to connect
7 projects asked. Not yet approved. Roughly what 779,000 homes use.
133 MW
has actually been built
6 projects switched on so far.
1.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 27%
  • Still waiting 32%
  • Withdrawn 41%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Richmond County.

What kind of power is asking to connect

  • Natural gas 44%
  • Solar 28%
  • Other 28%

By capacity requested. Data as of 14 October 2026.

All the numbers

22 requests ever filed
Pending applications
7
of 22 ever filed
Capacity queued
974 MW
requested, not committed
Already built
133 MW
6 projects connected
Built vs decided
40.0%
9 withdrawn
Median wait
1.5 yr
for applications still pending
Connected capacity
2.7 GW
indicator, see note

Source: interconnection queues published by Duke. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built6133 MW27.3%
Still waiting7974 MW31.8%
Withdrawn9916 MW40.9%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Natural gas5424 MW
Solar1275 MW
Other1275 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
170274Solar275 MWwithdrawn2021-04Duke
569986Solar275 MWwithdrawn2022-06Duke
923973Solar275 MWactive2023-09Duke
PP00046Other275 MWactive2025-08Duke
977773Natural gas260 MWactive2025-06Duke
909227Solar80 MWwithdrawn2023-09Duke
568778Solar65 MWwithdrawn2022-06Duke
200482Solar60 MWwithdrawn2020-03Duke
898595Solar60 MWwithdrawn2023-06Duke
PP00013Natural gas47 MWactive2025-04Duke
899591Natural gas47 MWactive2023-06Duke
610944Solar46 MWwithdrawn2023-04Duke
916613Solar46 MWwithdrawn2023-09Duke
957700Natural gas35 MWactive2024-06Duke
PP00014Natural gas35 MWactive2025-04Duke

How Richmond County compares

#380 in the US · #8 in NC

Richmond County ranks #380 of 1,607 US counties by power waiting to connect, and #8 of 44 in North Carolina.

CountyWaitingCapacity queued
Pinal County4610.6 GW
Person County41.9 GW
Washington County61.6 GW
Anson County31.5 GW
Davidson County21.5 GW
Wayne County231.3 GW
Stokes County31.2 GW
Robeson County9946 MW

Common questions about power in Richmond County

How long does it take to get power for a data center in Richmond County, NC?

The median wait for a project still in the interconnection queue in Richmond County is 1.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 6 projects in Richmond County have reached energization and 9 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Richmond County, NC?

974 MW is currently requested across 7 active interconnection requests, and 133 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Richmond County, NC a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our North Carolina policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Richmond County — Duke — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.