Data centers and new power in Stoddard County, MO

425 MW of new power is waiting to connect to the grid in Stoddard County, MO — 2 active requests. Typical wait: 2.9 years. 1 projects are built, 5 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Stoddard County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Stoddard County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Stoddard County right now.

425 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 340,000 homes use.
225 MW
has actually been built
1 projects switched on so far.
2.9 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 12%
  • Still waiting 25%
  • Withdrawn 62%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Stoddard County.

What kind of power is asking to connect

  • Not stated 53%
  • Solar 47%

By capacity requested. Data as of 14 October 2026.

All the numbers

8 requests ever filed
Pending applications
2
of 8 ever filed
Capacity queued
425 MW
requested, not committed
Already built
225 MW
1 projects connected
Built vs decided
16.7%
5 withdrawn
Median wait
2.9 yr
for applications still pending
Connected capacity
121 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built1225 MW12.5%
Still waiting2425 MW25.0%
Withdrawn5570 MW62.5%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Not stated1225 MW
Solar1200 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 8 by size
ProjectTypeCapacityStatusFiledQueue
5VANDUSERSolar230 MWwithdrawn2024-04MISO
Stoddard - Morley 161kV Line TapSolar225 MWcompleted2018-03MISO
Stoddard - Morley 161kVNot stated225 MWactive2025-02MISO
5STODDARD - 5MORLEY (AECI) 161kVSolar200 MWactive2022-09MISO
5STODDARD - 5MORLEY (AECI) 161.0kVSolar + battery140 MWwithdrawn2025-03MISO
Stoddart sub 161kVSolar100 MWwithdrawn2016-11MISO
Stoddard 161 kV SubstationSolar50 MWwithdrawn2022-09MISO
Stoddard - Morely 161 kV Line TapSolar50 MWwithdrawn2018-03MISO

How Stoddard County compares

#682 in the US · #9 in MO

Stoddard County ranks #682 of 1,607 US counties by power waiting to connect, and #9 of 26 in Missouri.

CountyWaitingCapacity queued
Randolph County133.5 GW
Clinton County41.4 GW
Jackson County8869 MW
Clay County6860 MW
Macon County3608 MW
Bollinger County3600 MW
Nodaway County2468 MW
New Madrid County6462 MW

Common questions about power in Stoddard County

How long does it take to get power for a data center in Stoddard County, MO?

The median wait for a project still in the interconnection queue in Stoddard County is 2.9 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Stoddard County have reached energization and 5 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Stoddard County, MO?

425 MW is currently requested across 2 active interconnection requests, and 225 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Stoddard County, MO a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Missouri policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Stoddard County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Stoddard County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Stoddard County on the map County reports All of Missouri