Jasper County, MO interconnection queue
2 interconnection applications are pending in Jasper County, MO, requesting 250 MW of new generating capacity, as of 15 August 2026. 0 projects have been built here and 16 have been withdrawn since 2003.
Source: interconnection queues published by SPP. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Jasper County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 2 | 250 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still pending | 2 | 250 MW | 11.1% |
| Withdrawn | 16 | 2.9 GW | 88.9% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| GEN-2003-011 | Gas | 600 MW | withdrawn | 2003-07 | SPP |
| GEN-2003-007 | Coal | 550 MW | withdrawn | 2003-07 | SPP |
| GI-94 | Solar | 225 MW | withdrawn | 2020-12 | AEC |
| GEN-2017-189 | Solar | 202 MW | withdrawn | 2017-11 | SPP |
| GI-68 | Solar | 200 MW | withdrawn | 2018-05 | AEC |
| GEN-2023-226 | Battery | 200 MW | withdrawn | 2023-10 | SPP |
| GEN-2020-088 | Solar | 150 MW | active | 2020-04 | SPP |
| GEN-2009-027 | Wind | 150 MW | withdrawn | 2009-07 | SPP |
| GEN-2009-028 | Wind | 150 MW | withdrawn | 2009-07 | SPP |
| GEN-2023-017 | Battery | 150 MW | withdrawn | 2023-10 | SPP |
| GEN-2021-059 | Solar | 130 MW | withdrawn | 2021-04 | SPP |
| GEN-2023-061 | Solar | 100 MW | active | 2023-10 | SPP |
| GEN-2018-053 | Wind | 100 MW | withdrawn | 2018-05 | SPP |
| GI-45 | Wind | 80 MW | withdrawn | 2011-02 | AEC |
| GEN-2023-233 | Battery | 75 MW | withdrawn | 2023-10 | SPP |
How this county ranks
Jasper County ranks #848 of 1,607 US counties by capacity currently queued, and #15 of 26 in Missouri.
Other Missouri counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Randolph County | 13 | 3.5 GW |
| Clinton County | 4 | 1.4 GW |
| Clay County | 5 | 850 MW |
| Jackson County | 6 | 849 MW |
| Macon County | 3 | 608 MW |
| Bollinger County | 3 | 600 MW |
| Nodaway County | 2 | 468 MW |
| New Madrid County | 6 | 462 MW |
Go deeper on Jasper County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.
Open Jasper County on the map County reports All of Missouri