Data centers and new power in Clay County, MO

860 MW of new power is waiting to connect to the grid in Clay County, MO — 6 active requests. Typical wait: 2.5 years. 0 projects are built, 2 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Clay County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Clay County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Clay County right now.

860 MW
of new power is waiting to connect
6 projects asked. Not yet approved. Roughly what 688,000 homes use.
0 MW
has actually been built
0 projects switched on so far.
2.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Still waiting 75%
  • Withdrawn 25%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Clay County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

8 requests ever filed
Pending applications
6
of 8 ever filed
Capacity queued
860 MW
requested, not committed
Already built
0 MW
0 projects connected
Built vs decided
0.0%
2 withdrawn
Median wait
2.5 yr
for applications still pending

Source: interconnection queues published by SPP. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built00 MW0.0%
Still waiting6860 MW75.0%
Withdrawn2200 MW25.0%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar6860 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source
SPPSPP 2028 CPP Interconnection Cluster Study (ICS) application window
Definitive Interconnection System Impact Study cluster, post Order 2023 compliance.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 8 by size
ProjectTypeCapacityStatusFiledQueue
GEN-2024-370Solar250 MWactive2025-03SPP
GEN-2023-033Solar200 MWactive2023-10SPP
GEN-2022-142Solar200 MWactive2023-02SPP
GEN-2023-169Batteries125 MWwithdrawn2023-10SPP
GEN-2024-090Solar100 MWactive2024-10SPP
GEN-2022-102Solar100 MWactive2023-01SPP
GEN-2022-125Batteries75 MWwithdrawn2023-02SPP
AFS NJG-2026-001Solar10 MWactive2026-01SPP

How Clay County compares

#443 in the US · #4 in MO

Clay County ranks #443 of 1,607 US counties by power waiting to connect, and #4 of 26 in Missouri.

CountyWaitingCapacity queued
Randolph County133.5 GW
Clinton County41.4 GW
Jackson County8869 MW
Macon County3608 MW
Bollinger County3600 MW
Nodaway County2468 MW
New Madrid County6462 MW
Stoddard County2425 MW

Common questions about power in Clay County

How long does it take to get power for a data center in Clay County, MO?

The median wait for a project still in the interconnection queue in Clay County is 2.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Clay County have reached energization and 2 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Clay County, MO?

860 MW is currently requested across 6 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Clay County, MO a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Missouri policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Clay County — SPP — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Clay County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Clay County on the map County reports All of Missouri