Wilcox County, GA interconnection queue
2 interconnection applications are pending in Wilcox County, GA, requesting 210 MW of new generating capacity, as of 15 August 2026. 0 projects have been built here and 2 have been withdrawn since 2016.
Source: interconnection queues published by GTC. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Wilcox County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 2 | 210 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 0 | 0 MW | 0.0% |
| Still pending | 2 | 210 MW | 40.0% |
| Withdrawn | 2 | 318 MW | 40.0% |
| Suspended | 1 | — | 20.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| IC-1238 | Solar | 250 MW | withdrawn | 2024-01 | SOCO |
| IC-1153 | Solar | 150 MW | suspended | 2023-07 | SOCO |
| SR Rochelle Solar | Solar | 120 MW | active | 2021-12 | GTC |
| SR Rochelle II Solar | Solar | 90 MW | active | 2023-09 | GTC |
| IC-512 | Solar | 68 MW | withdrawn | 2016-10 | SOCO |
How this county ranks
Wilcox County ranks #892 of 1,607 US counties by capacity currently queued, and #32 of 61 in Georgia.
Other Georgia counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Heard County | 7 | 4.2 GW |
| Bartow County | 7 | 3.6 GW |
| Coweta County | 6 | 2.6 GW |
| Mitchell County | 6 | 2.4 GW |
| Monroe County | 1 | 2.0 GW |
| Hancock County | 4 | 2.0 GW |
| Effingham County | 13 | 1.9 GW |
| Sumter County | 5 | 1.4 GW |
Go deeper on Wilcox County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.