Data centers and new power in Clarke-Jackson Co, GA

0 MW of new power is waiting to connect to the grid in Clarke-Jackson Co, GA — 0 active requests. 1 projects are built, 9 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Clarke-Jackson Co itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Clarke-Jackson Co

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Clarke-Jackson Co right now.

0 MW
of new power is waiting to connect
0 projects asked. Not yet approved.
4 MW
has actually been built
1 projects switched on so far.
9
projects gave up
Withdrawn before being built. Normal nationally.

Where every request ever filed here ended up

  • Built 10%
  • Withdrawn 90%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Clarke-Jackson Co.

What kind of power is asking to connect

    By capacity requested. Data as of 14 October 2026.

    All the numbers

    10 requests ever filed
    Pending applications
    0
    of 10 ever filed
    Capacity queued
    0 MW
    requested, not committed
    Already built
    4 MW
    1 projects connected
    Built vs decided
    10.0%
    9 withdrawn

    Source: interconnection queues published by the transmission providers serving this county. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

    Outcome of every request filed here

    OutcomeProjectsCapacityShare
    Built14 MW10.0%
    Still waiting00 MW0.0%
    Withdrawn93.6 GW90.0%
    Paused0—0.0%

    Waiting to connect, by type of power

    Key dates for projects here

    no dated windows published
    QueueWhat closesClosesStanding
    FERCFERC large-load show cause — stakeholder comments on RTO responses
    Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
    No date published yetunconfirmed source
    FERCFERC RM26-4 — generic large-load rulemaking
    Still at ANOPR stage.
    No date published yetconfirmed source
    FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
    A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
    No date published yetconfirmed source

    A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

    The biggest projects on file

    top 10 by size
    ProjectTypeCapacityStatusFiledQueue
    IC-014Natural gas620 MWwithdrawn—SOCO
    IC-015Natural gas620 MWwithdrawn—SOCO
    IC-016Natural gas620 MWwithdrawn—SOCO
    IC-077Natural gas564 MWwithdrawn—SOCO
    IC-131Natural gas564 MWwithdrawn—SOCO
    IC-034Natural gas185 MWwithdrawn—SOCO
    IC-035Natural gas185 MWwithdrawn—SOCO
    IC-1186Batteries130 MWwithdrawn2023-10SOCO
    IC-1181Batteries100 MWwithdrawn2023-10SOCO
    Fall Line Hydro (aka Tallasee Shoals)Hydro4 MWcompleted2023-12GTC

    How Clarke-Jackson Co compares

    #1284 in the US · #50 in GA

    Clarke-Jackson Co ranks #1284 of 1,607 US counties by power waiting to connect, and #50 of 61 in Georgia.

    CountyWaitingCapacity queued
    Heard County74.2 GW
    Bartow County73.6 GW
    Coweta County62.6 GW
    Mitchell County62.4 GW
    Monroe County12.0 GW
    Hancock County42.0 GW
    Effingham County131.9 GW
    Sumter County51.4 GW

    Common questions about power in Clarke-Jackson Co

    How long does it take to get power for a data center in Clarke-Jackson Co, GA?

    We do not yet have a median wait for Clarke-Jackson Co. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Clarke-Jackson Co have reached energization and 9 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

    How much capacity is available in Clarke-Jackson Co, GA?

    0 MW is currently requested across 0 active interconnection requests, and 4 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

    Is Clarke-Jackson Co, GA a good site for a data center?

    This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Georgia policy page.

    Where does the data on this page come from?

    The interconnection queue published by the transmission providers serving Clarke-Jackson Co — the utilities in this area — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.