Data centers and new power in Chatham County, GA

0 MW of new power is waiting to connect to the grid in Chatham County, GA — 0 active requests. 1 projects are built, 6 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Chatham County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Chatham County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Chatham County right now.

0 MW
of new power is waiting to connect
0 projects asked. Not yet approved.
30 MW
has actually been built
1 projects switched on so far.
6
projects gave up
Withdrawn before being built. Normal nationally.

Where every request ever filed here ended up

  • Built 14%
  • Withdrawn 86%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Chatham County.

What kind of power is asking to connect

    By capacity requested. Data as of 14 October 2026.

    All the numbers

    7 requests ever filed
    Pending applications
    0
    of 7 ever filed
    Capacity queued
    0 MW
    requested, not committed
    Already built
    30 MW
    1 projects connected
    Built vs decided
    14.3%
    6 withdrawn

    Source: interconnection queues published by the transmission providers serving this county. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

    Outcome of every request filed here

    OutcomeProjectsCapacityShare
    Built130 MW14.3%
    Still waiting00 MW0.0%
    Withdrawn63.2 GW85.7%
    Paused0—0.0%

    Waiting to connect, by type of power

    Key dates for projects here

    no dated windows published
    QueueWhat closesClosesStanding
    FERCFERC large-load show cause — stakeholder comments on RTO responses
    Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
    No date published yetunconfirmed source
    FERCFERC RM26-4 — generic large-load rulemaking
    Still at ANOPR stage.
    No date published yetconfirmed source
    FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
    A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
    No date published yetconfirmed source

    A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

    The biggest projects on file

    top 7 by size
    ProjectTypeCapacityStatusFiledQueue
    IC-051Natural gas800 MWwithdrawn—SOCO
    IC-093Natural gas640 MWwithdrawn—SOCO
    IC-052Natural gas613 MWwithdrawn—SOCO
    IC-119Natural gas550 MWwithdrawn—SOCO
    IC-099Natural gas533 MWwithdrawn—SOCO
    IC-1155Batteries50 MWwithdrawn2023-07SOCO
    Weyerhaeuser Port WentworthNatural gas30 MWcompleted—SOCO

    How Chatham County compares

    #1283 in the US · #49 in GA

    Chatham County ranks #1283 of 1,607 US counties by power waiting to connect, and #49 of 61 in Georgia.

    CountyWaitingCapacity queued
    Heard County74.2 GW
    Bartow County73.6 GW
    Coweta County62.6 GW
    Mitchell County62.4 GW
    Monroe County12.0 GW
    Hancock County42.0 GW
    Effingham County131.9 GW
    Sumter County51.4 GW

    Common questions about power in Chatham County

    How long does it take to get power for a data center in Chatham County, GA?

    We do not yet have a median wait for Chatham County. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Chatham County have reached energization and 6 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

    How much capacity is available in Chatham County, GA?

    0 MW is currently requested across 0 active interconnection requests, and 30 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

    Is Chatham County, GA a good site for a data center?

    This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Georgia policy page.

    Where does the data on this page come from?

    The interconnection queue published by the transmission providers serving Chatham County — the utilities in this area — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

    Go deeper on Chatham County

    The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

    Open Chatham County on the map County reports All of Georgia