Data centers and new power in Lake County, FL

0 MW of new power is waiting to connect to the grid in Lake County, FL — 0 active requests. 0 projects are built, 10 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Lake County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Lake County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Lake County right now.

0 MW
of new power is waiting to connect
0 projects asked. Not yet approved.
0 MW
has actually been built
0 projects switched on so far.
10
projects gave up
Withdrawn before being built. Normal nationally.

Where every request ever filed here ended up

  • Withdrawn 100%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Lake County.

What kind of power is asking to connect

    By capacity requested. Data as of 14 October 2026.

    All the numbers

    10 requests ever filed
    Pending applications
    0
    of 10 ever filed
    Capacity queued
    0 MW
    requested, not committed
    Already built
    0 MW
    0 projects connected
    Built vs decided
    0.0%
    10 withdrawn

    Source: interconnection queues published by the transmission providers serving this county. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

    Outcome of every request filed here

    OutcomeProjectsCapacityShare
    Built00 MW0.0%
    Still waiting00 MW0.0%
    Withdrawn102.7 GW100.0%
    Paused0—0.0%

    Waiting to connect, by type of power

    Key dates for projects here

    no dated windows published
    QueueWhat closesClosesStanding
    FERCFERC large-load show cause — stakeholder comments on RTO responses
    Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
    No date published yetunconfirmed source
    FERCFERC RM26-4 — generic large-load rulemaking
    Still at ANOPR stage.
    No date published yetconfirmed source
    FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
    A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
    No date published yetconfirmed source

    A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

    The biggest projects on file

    top 10 by size
    ProjectTypeCapacityStatusFiledQueue
    9Natural gas662 MWwithdrawn2000-07Duke
    21Natural gas597 MWwithdrawn2004-12Duke
    22Natural gas597 MWwithdrawn2004-12Duke
    23Natural gas597 MWwithdrawn2004-12Duke
    120Other110 MWwithdrawn2013-06Duke
    113Solar100 MWwithdrawn2011-08Duke
    192Solar25 MWwithdrawn2017-08Duke
    188Solar20 MWwithdrawn2017-06Duke
    122Other16 MWwithdrawn2013-08Duke
    127Other11 MWwithdrawn2013-10Duke

    How Lake County compares

    #1279 in the US · #45 in FL

    Lake County ranks #1279 of 1,607 US counties by power waiting to connect, and #45 of 48 in Florida.

    CountyWaitingCapacity queued
    Hendry County403.0 GW
    Miami-Dade County32.7 GW
    Osceola County92.0 GW
    St. Lucie County241.8 GW
    DeSoto County161.2 GW
    Collier County151.1 GW
    Charlotte County141.0 GW
    Martin County141.0 GW

    Common questions about power in Lake County

    How long does it take to get power for a data center in Lake County, FL?

    We do not yet have a median wait for Lake County. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 0 projects in Lake County have reached energization and 10 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

    How much capacity is available in Lake County, FL?

    0 MW is currently requested across 0 active interconnection requests, and 0 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

    Is Lake County, FL a good site for a data center?

    This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Florida policy page.

    Where does the data on this page come from?

    The interconnection queue published by the transmission providers serving Lake County — the utilities in this area — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

    Go deeper on Lake County

    The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

    Open Lake County on the map County reports All of Florida