Data centers and new power in Hendry County, FL

3.0 GW of new power is waiting to connect to the grid in Hendry County, FL — 40 active requests. Typical wait: 3.8 years. 6 projects are built, 3 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Hendry County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Hendry County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Hendry County right now.

3.0 GW
of new power is waiting to connect
40 projects asked. Not yet approved. Roughly what 2.4 million homes use.
447 MW
has actually been built
6 projects switched on so far.
3.8 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 12%
  • Still waiting 82%
  • Withdrawn 6%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Hendry County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

49 requests ever filed
Pending applications
40
of 49 ever filed
Capacity queued
3.0 GW
requested, not committed
Already built
447 MW
6 projects connected
Built vs decided
66.7%
3 withdrawn
Median wait
3.8 yr
for applications still pending
Connected capacity
720 MW
indicator, see note

Source: interconnection queues published by FPL. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built6447 MW12.2%
Still waiting403.0 GW81.6%
Withdrawn3574 MW6.1%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar403.0 GW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
631Batteries300 MWwithdrawn2024-01FPL
630Batteries200 MWwithdrawn2024-01FPL
206Solar74 MWcompleted2016-09FPL
277Solar74 MWcompleted2017-06FPL
278Solar74 MWcompleted2017-06FPL
279Solar74 MWcompleted2017-06FPL
280Solar74 MWactive2017-06FPL
337Solar74 MWcompleted2018-03FPL
338Solar74 MWcompleted2018-03FPL
339Solar74 MWactive2018-03FPL
431Solar74 MWactive2022-03FPL
438Solar74 MWactive2022-03FPL
522Solar74 MWactive2023-01FPL
523Solar74 MWactive2023-01FPL
524Solar74 MWactive2023-01FPL

How Hendry County compares

#115 in the US · #1 in FL

Hendry County ranks #115 of 1,607 US counties by power waiting to connect, and #1 of 48 in Florida.

CountyWaitingCapacity queued
Miami-Dade County32.7 GW
Osceola County92.0 GW
St. Lucie County241.8 GW
DeSoto County161.2 GW
Collier County151.1 GW
Charlotte County141.0 GW
Martin County141.0 GW
Duval County6995 MW

Common questions about power in Hendry County

How long does it take to get power for a data center in Hendry County, FL?

The median wait for a project still in the interconnection queue in Hendry County is 3.8 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 6 projects in Hendry County have reached energization and 3 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Hendry County, FL?

3.0 GW is currently requested across 40 active interconnection requests, and 447 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Hendry County, FL a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Florida policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Hendry County — FPL — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Hendry County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Hendry County on the map County reports All of Florida