Vermont interconnection queue

5 interconnection applications are pending in Vermont, requesting 129 MW of new generating capacity across 9 counties, as of 15 August 2026. That places Vermont #46 of 47 states by capacity queued.

Pending applications
5
of 109 ever filed
Capacity queued
129 MW
requested, not committed
Already built
933 MW
17 connected
Built vs decided
16.3%
87 withdrawn
Counties in the queue
9
with five or more filings
Large load requested
none recorded
0 requests

Source: the interconnection queues of every transmission provider operating in Vermont. Parsed and normalised by Watt Street. Data as of 15 August 2026.

Which queues serve Vermont

Queue or utilityApplicationsCapacity pending
ISONE109129 MW

What is waiting in Vermont, by fuel

FuelProjectsCapacity requested
Solar390 MW
Battery239 MW

Counties with the most capacity queued

CountyPendingCapacity queuedAlready built
Addison County150 MW0 MW
Bennington County120 MW30 MW
Rutland County120 MW3 MW
Franklin County119 MW42 MW
Windsor County119 MW60 MW
Caledonia County00 MW40 MW
Chittenden County00 MW12 MW
Orleans County00 MW65 MW
Windham County00 MW669 MW