Data centers and new power in Rutland County, VT
20 MW of new power is waiting to connect to the grid in Rutland County, VT — 1 active requests. Typical wait: 9.2 years. 1 projects are built, 11 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Rutland County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Rutland County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Rutland County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Rutland County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
13 requests ever filed
Source: interconnection queues published by ISONE. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 1 | 3 MW | 7.7% |
| Still waiting | 1 | 20 MW | 7.7% |
| Withdrawn | 11 | 1.3 GW | 84.6% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar | 1 | 20 MW |
Key dates for projects here
1 dated · next closes 2026-11-19 (ISONE)
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| ISONE | ISO-NE cluster request window Cluster study under OATT Schedules 22, 23 and 25. | 2026-11-19 | disputed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 13 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| HVDC Tie - Import only | Nuclear | 1.0 GW | withdrawn | 2015-02 | ISONE |
| Wind | Wind | 85 MW | withdrawn | 2008-10 | ISONE |
| Wind Project | Wind | 60 MW | withdrawn | 2006-09 | ISONE |
| Fair Haven Biomass | Solar | 33 MW | withdrawn | 2010-05 | ISONE |
| Solar | Solar | 22 MW | withdrawn | 2018-04 | ISONE |
| Solar | Solar | 20 MW | withdrawn | 2015-09 | ISONE |
| Fair Haven Solar | Solar | 20 MW | active | 2017-08 | ISONE |
| Solar | Solar | 20 MW | withdrawn | 2015-09 | ISONE |
| Davenport Solar | Solar | 15 MW | withdrawn | 2018-04 | ISONE |
| Proctor Hydroelectric Station Uprate | Wind | 3 MW | completed | 2015-03 | ISONE |
| Hydro | Wind | 1 MW | withdrawn | 2014-11 | ISONE |
| Rutland Energy Park | Not stated | — | withdrawn | 1998-09 | ISONE |
| 1000 MW HVDC Tie V2 (See Q425) | Nuclear | — | withdrawn | 2013-10 | ISONE |
How Rutland County compares
#1219 in the US · #3 in VT
Rutland County ranks #1219 of 1,607 US counties by power waiting to connect, and #3 of 9 in Vermont.
| County | Waiting | Capacity queued |
|---|---|---|
| Addison County | 1 | 50 MW |
| Bennington County | 1 | 20 MW |
| Caledonia County | 0 | 0 MW |
| Chittenden County | 0 | 0 MW |
| Franklin County | 0 | 0 MW |
| Orleans County | 0 | 0 MW |
| Windham County | 0 | 0 MW |
| Windsor County | 0 | 0 MW |
Common questions about power in Rutland County
How long does it take to get power for a data center in Rutland County, VT?
The median wait for a project still in the interconnection queue in Rutland County is 9.2 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Rutland County have reached energization and 11 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Rutland County, VT?
20 MW is currently requested across 1 active interconnection requests, and 3 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Rutland County, VT a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Vermont policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Rutland County — ISONE — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.