Sign in

TEC interconnection queue

10 interconnection requests are active in TEC, totalling 0.6 GW, as of 15 August 2026. Of the 108 requests ever filed here, 31 were built and 67 were withdrawn — a build rate of 31.6% on decided applications.

Active requests
10
of 108 ever filed
Capacity queued
0.6 GW
requested, not committed
Built vs decided
31.6%
31 built, 67 withdrawn
Median wait so far
1.9 yr
for requests still active
Median time to build
1.8 yr
request to commercial operation

Source: the TEC interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.

What is queued in TEC, by fuel

FuelProjectsCapacity requested
Solar8556 MW
Other148 MW
Battery120 MW

Where TEC’s queue sits

StateApplicationsCapacity pending
Florida105624 MW

Largest active requests

ProjectFuelCapacityCountyStateFiled
118Solar132 MWPolk CountyFL2025-04
101Solar74 MWHillsborough CountyFL2023-04
112Solar74 MWHillsborough CountyFL2024-03
121Solar74 MWHillsborough CountyFL2025-05
122Solar74 MWHillsborough CountyFL2025-05
76Solar55 MWPolk CountyFL2020-11
111Solar52 MWPolk CountyFL2024-03
70Other48 MWPolk CountyFL2020-05
120Battery20 MWPolk CountyFL2025-05
123Solar20 MWPolk CountyFL2025-05

TEC on the map

Open the map Every queue we track