TEC interconnection queue
10 interconnection requests are active in TEC, totalling 0.6 GW, as of 15 August 2026. Of the 108 requests ever filed here, 31 were built and 67 were withdrawn — a build rate of 31.6% on decided applications.
Active requests
10
of 108 ever filed
Capacity queued
0.6 GW
requested, not committed
Built vs decided
31.6%
31 built, 67 withdrawn
Median wait so far
1.9 yr
for requests still active
Median time to build
1.8 yr
request to commercial operation
Source: the TEC interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.
What is queued in TEC, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 8 | 556 MW |
| Other | 1 | 48 MW |
| Battery | 1 | 20 MW |
Where TEC’s queue sits
| State | Applications | Capacity pending |
|---|---|---|
| Florida | 105 | 624 MW |
Largest active requests
| Project | Fuel | Capacity | County | State | Filed |
|---|---|---|---|---|---|
| 118 | Solar | 132 MW | Polk County | FL | 2025-04 |
| 101 | Solar | 74 MW | Hillsborough County | FL | 2023-04 |
| 112 | Solar | 74 MW | Hillsborough County | FL | 2024-03 |
| 121 | Solar | 74 MW | Hillsborough County | FL | 2025-05 |
| 122 | Solar | 74 MW | Hillsborough County | FL | 2025-05 |
| 76 | Solar | 55 MW | Polk County | FL | 2020-11 |
| 111 | Solar | 52 MW | Polk County | FL | 2024-03 |
| 70 | Other | 48 MW | Polk County | FL | 2020-05 |
| 120 | Battery | 20 MW | Polk County | FL | 2025-05 |
| 123 | Solar | 20 MW | Polk County | FL | 2025-05 |