23 interconnection requests are active in PGE, totalling 6.4 GW, as of 15 August 2026. Of the 114 requests ever filed here, 6 were built and 51 were withdrawn — a build rate of 10.5% on decided applications.

Active requests
23
of 114 ever filed
Capacity queued
6.4 GW
requested, not committed
Built vs decided
10.5%
6 built, 51 withdrawn
Median wait so far
3.5 yr
for requests still active
Median time to build
2.9 yr
request to commercial operation

Source: the PGE interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.

What is queued in PGE, by fuel

FuelProjectsCapacity requested
Solar62.8 GW
Battery132.6 GW
Wind41.0 GW

Where PGE’s queue sits

StateApplicationsCapacity pending
Oregon1126.4 GW
Washington20 MW

Largest active requests

ProjectFuelCapacityCountyStateFiled
23-233Solar800 MWJefferson CountyOR2023-06
23-234Solar800 MWJefferson CountyOR2023-06
23-229Solar750 MWJefferson CountyOR2023-03
21-104Battery400 MWWashington CountyOR2021-08
23-221Battery400 MWWashington CountyOR2023-03
21-098Solar250 MWJefferson CountyOR2021-04
23-226Wind250 MWJefferson CountyOR2023-03
23-227Wind250 MWJefferson CountyOR2023-03
23-228Wind250 MWJefferson CountyOR2023-03
23-231Wind250 MWJefferson CountyOR2023-03
17-067Battery200 MWMultnomah CountyOR2017-09
21-099Battery200 MWWashington CountyOR2021-05
21-100Battery200 MWWashington CountyOR2021-05
21-102Battery200 MWMultnomah CountyOR2021-05
21-103Battery200 MWClackamas CountyOR2021-05

PGE on the map