33 interconnection requests are active in NWMT, totalling 7.1 GW, as of 15 August 2026. Of the 448 requests ever filed here, 71 were built and 328 were withdrawn — a build rate of 17.8% on decided applications.
Active requests
33
of 448 ever filed
Capacity queued
7.1 GW
requested, not committed
Built vs decided
17.8%
71 built, 328 withdrawn
Median wait so far
3.9 yr
for requests still active
Median time to build
1.2 yr
request to commercial operation
Source: the NWMT interconnection queue as published by the transmission provider, parsed and normalised by Watt Street. Data as of 15 August 2026. Wait times are medians over requests that carry a measured date.
What is queued in NWMT, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Wind | 9 | 4.2 GW |
| Solar | 13 | 2.3 GW |
| Gas | 7 | 494 MW |
| Battery | 1 | 100 MW |
| Hydro | 3 | 83 MW |
Where NWMT’s queue sits
| State | Applications | Capacity pending |
|---|---|---|
| Montana | 429 | 7.1 GW |
| South Dakota | 17 | 8 MW |
Largest active requests
| Project | Fuel | Capacity | County | State | Filed |
|---|---|---|---|---|---|
| 435 | Solar | 800 MW | Rosebud County | MT | 2022-11 |
| 356 | Wind | 750 MW | Rosebud County | MT | 2018-10 |
| 357 | Wind | 750 MW | Rosebud County | MT | 2018-10 |
| 418 | Wind | 750 MW | Wheatland County | MT | 2022-01 |
| 361 | Wind | 600 MW | Wheatland County | MT | 2019-03 |
| 390 | Solar | 500 MW | Yellowstone County | MT | 2020-08 |
| 408 | Wind | 326 MW | Wheatland County | MT | 2021-02 |
| 300 | Wind | 315 MW | Stillwater County | MT | 2016-07 |
| 311 | Solar | 300 MW | Yellowstone County | MT | 2017-02 |
| 406 | Wind | 300 MW | Rosebud County | MT | 2021-02 |
| 407 | Wind | 300 MW | Rosebud County | MT | 2021-02 |
| 419 | Solar | 300 MW | Big Horn County | MT | 2022-02 |
| 378 | Gas | 175 MW | Yellowstone County | MT | 2020-05 |
| 464 | Gas | 150 MW | Broadwater County | MT | 2024-06 |
| 465 | Gas | 150 MW | Stillwater County | MT | 2024-06 |