Miller, UT interconnection queue
27 interconnection applications are pending in Miller, UT, requesting 6.5 GW of new generating capacity, as of 15 August 2026. 3 projects have been built here and 52 have been withdrawn since 2008.
Source: interconnection queues published by LADWP, PacifiCorp. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Miller, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 23 | 6.0 GW |
| Wind | 1 | 300 MW |
| Gas | 1 | 185 MW |
| Geothermal | 2 | 40 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 3 | 120 MW | 3.6% |
| Still pending | 27 | 6.5 GW | 32.1% |
| Withdrawn | 52 | 6.3 GW | 61.9% |
| Suspended | 2 | — | 2.4% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Q93 | Solar | 1.0 GW | active | 2022-08 | LADWP |
| C4-033 | Wind | 600 MW | withdrawn | 2024-05 | PacifiCorp |
| T2-092 | Wind | 600 MW | withdrawn | 2025-09 | PacifiCorp |
| Q105 | Solar | 600 MW | active | 2023-06 | LADWP |
| C3-036 | Solar | 500 MW | active | 2023-05 | PacifiCorp |
| C1-32 | Wind | 456 MW | withdrawn | 2021-05 | PacifiCorp |
| C2-78 | Wind | 456 MW | withdrawn | 2022-05 | PacifiCorp |
| Q104 | Solar | 400 MW | active | 2023-06 | LADWP |
| Q50 | Solar | 400 MW | active | 2016-01 | LADWP |
| Q51 | Solar | 400 MW | active | 2016-01 | LADWP |
| Q77 | Solar | 400 MW | withdrawn | 2020-04 | LADWP |
| Q90 | Solar | 400 MW | active | 2022-04 | LADWP |
| Q94 | Solar | 400 MW | active | 2022-12 | LADWP |
| 343 | Wind | 398 MW | withdrawn | 2010-06 | PacifiCorp |
| Q52 | Solar | 324 MW | active | 2016-01 | LADWP |
How this county ranks
Miller ranks #31 of 1,607 US counties by capacity currently queued, and #1 of 21 in Utah.
Other Utah counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Utah County | 29 | 6.0 GW |
| Emery County | 19 | 3.5 GW |
| Juab County | 15 | 3.2 GW |
| Salt Lake County | 11 | 2.3 GW |
| Iron County | 11 | 1.8 GW |
| Kane County | 3 | 1.1 GW |
| Washington County | 4 | 780 MW |
| Box Elder County | 5 | 765 MW |
Go deeper on Miller