Teton County, MT interconnection queue
0 interconnection applications are pending in Teton County, MT, requesting 0 MW of new generating capacity, as of 15 August 2026. 5 projects have been built here and 12 have been withdrawn since 2006.
Source: interconnection queues published by the transmission providers serving this county. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Teton County, by fuel
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 5 | 48 MW | 29.4% |
| Still pending | 0 | 0 MW | 0.0% |
| Withdrawn | 12 | 187 MW | 70.6% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| 288 | Wind | 20 MW | withdrawn | 2016-06 | NWMT |
| 344 | Wind | 20 MW | withdrawn | 2018-06 | NWMT |
| 355 | Wind | 20 MW | withdrawn | 2018-09 | NWMT |
| 84 | Wind | 20 MW | withdrawn | 2008-03 | NWMT |
| 127 | Wind | 20 MW | withdrawn | 2010-10 | NWMT |
| 102 | Wind | 19 MW | withdrawn | 2009-01 | NWMT |
| 48 | Wind | 19 MW | withdrawn | 2006-06 | NWMT |
| 50 | Wind | 19 MW | withdrawn | 2006-06 | NWMT |
| 153 | Wind | 15 MW | completed | 2012-08 | NWMT |
| 51 | Hydro | 15 MW | withdrawn | 2006-08 | NWMT |
| 62 | Hydro | 12 MW | completed | 2007-05 | NWMT |
| 132 | Wind | 10 MW | withdrawn | 2011-03 | NWMT |
| 133 | Wind | 10 MW | completed | 2011-03 | NWMT |
| 134 | Wind | 10 MW | completed | 2011-03 | NWMT |
| 263 | Solar | 3 MW | withdrawn | 2016-03 | NWMT |
How this county ranks
Teton County ranks #1420 of 1,607 US counties by capacity currently queued, and #28 of 29 in Montana.
Other Montana counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Wheatland County | 8 | 3.2 GW |
| Rosebud County | 5 | 2.9 GW |
| Meagher County | 4 | 1.5 GW |
| Yellowstone County | 6 | 1.2 GW |
| Big Horn County | 3 | 608 MW |
| Stillwater County | 4 | 595 MW |
| Broadwater County | 2 | 160 MW |
| Cascade County | 1 | 70 MW |