Data centers and new power in Washington County, MS
170 MW of new power is waiting to connect to the grid in Washington County, MS — 1 active requests. Typical wait: 0.9 years. 1 projects are built, 9 withdrawn. Data as of 14 October 2026.
Is one near your house?
We have not mapped a large AI data center inside Washington County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.
What is happening with electricity in Washington County
Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Washington County right now.
Where every request ever filed here ended up
Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Washington County.
What kind of power is asking to connect
By capacity requested. Data as of 14 October 2026.
All the numbers
11 requests ever filed
Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.
Outcome of every request filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 1 | 200 MW | 9.1% |
| Still waiting | 1 | 170 MW | 9.1% |
| Withdrawn | 9 | 1.7 GW | 81.8% |
| Paused | 0 | — | 0.0% |
Waiting to connect, by type of power
| Type | Projects | Capacity requested |
|---|---|---|
| Solar | 1 | 170 MW |
Key dates for projects here
1 dated · next closes 2027-09-10 (MISO)
| Queue | What closes | Closes | Standing |
|---|---|---|---|
| MISO | MISO DPP-2026 Definitive Planning Phase application deadline Attachment X of the tariff and BPM-015. | 2027-09-10 | confirmed source |
| FERC | FERC large-load show cause — stakeholder comments on RTO responses Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70… | No date published yet | unconfirmed source |
| FERC | FERC RM26-4 — generic large-load rulemaking Still at ANOPR stage. | No date published yet | confirmed source |
| FERC | Georgia PSC - Georgia Power must file large-load contracts 30 days before execution A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed. | No date published yet | confirmed source |
A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.
The biggest projects on file
top 11 by size
| Project | Type | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| Indianola to Gerald Andrus 230 kV | Solar | 350 MW | withdrawn | 2021-08 | MISO |
| GERALD ANDRUS SES SWYD - INDIANOLA 230/115 SUB 230.0kV | Solar | 300 MW | withdrawn | 2025-09 | MISO |
| Gerald Andrus 230 kV | Solar + battery | 200 MW | withdrawn | 2024-04 | MISO |
| Gerald Andrus - Clinton Industrial 230 kV Line | Solar | 200 MW | withdrawn | 2017-06 | MISO |
| Ray Braswell - Tinnin - Gerald Andrus 230kV Line | Solar | 200 MW | completed | 2019-04 | MISO |
| Gerald Andrus 230 kV Substation | Solar | 200 MW | withdrawn | 2024-04 | MISO |
| Stringtown-Greenville/North 115kV Transmission Line | Solar | 200 MW | withdrawn | 2022-09 | MISO |
| GERALD ANDRUS SES SWYD - TINNIN ROAD 230.0kV | Solar | 170 MW | active | 2025-11 | MISO |
| SE Greenville 115kV Substation | Solar | 100 MW | withdrawn | 2018-03 | MISO |
| HOLLANDALE - NITTA YUMA SS (CE) 115.0kV | Solar + battery | 100 MW | withdrawn | 2022-09 | MISO |
| Greer Solar substation J1458 | Solar | 50 MW | withdrawn | 2024-04 | MISO |
How Washington County compares
#977 in the US · #14 in MS
Washington County ranks #977 of 1,607 US counties by power waiting to connect, and #14 of 31 in Mississippi.
| County | Waiting | Capacity queued |
|---|---|---|
| Clay County | 5 | 850 MW |
| Madison County | 5 | 827 MW |
| Lowndes County | 2 | 820 MW |
| Sunflower County | 5 | 807 MW |
| Perry County | 3 | 500 MW |
| Holmes County | 2 | 425 MW |
| Jasper County | 3 | 365 MW |
| DeSoto County | 2 | 350 MW |
Common questions about power in Washington County
How long does it take to get power for a data center in Washington County, MS?
The median wait for a project still in the interconnection queue in Washington County is 0.9 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 1 projects in Washington County have reached energization and 9 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.
How much capacity is available in Washington County, MS?
170 MW is currently requested across 1 active interconnection requests, and 200 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.
Is Washington County, MS a good site for a data center?
This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Mississippi policy page.
Where does the data on this page come from?
The interconnection queue published by the transmission providers serving Washington County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.
Go deeper on Washington County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.
Open Washington County on the map County reports All of Mississippi