Lenawee County, MI interconnection queue
7 interconnection applications are pending in Lenawee County, MI, requesting 1.3 GW of new generating capacity, as of 15 August 2026. 5 projects have been built here and 6 have been withdrawn since 2017.
Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 15 August 2026. A queued project is a request, not a commitment.
What is waiting in Lenawee County, by fuel
| Fuel | Projects | Capacity requested |
|---|---|---|
| Solar | 4 | 740 MW |
| Wind | 3 | 575 MW |
Outcomes of every application filed here
| Outcome | Projects | Capacity | Share |
|---|---|---|---|
| Built | 5 | 705 MW | 27.8% |
| Still pending | 7 | 1.3 GW | 38.9% |
| Withdrawn | 6 | 690 MW | 33.3% |
| Suspended | 0 | — | 0.0% |
Withdrawal is the ordinary outcome of an interconnection application nationally, not a sign of a problem in this county. Most withdrawals are a developer testing a site and moving on.
The largest projects on file
| Project | Fuel | Capacity | Status | Filed | Queue |
|---|---|---|---|---|---|
| MOROCCO - ALLEN JUNCTION 345.0kV | Wind | 263 MW | active | 2024-04 | MISO |
| BEECHER - KNOWLES 138.0kV | Solar | 250 MW | active | 2025-05 | MISO |
| MOROCCO | Solar | 200 MW | completed | 2021-12 | MISO |
| Morocco 345 kV Substation | Solar | 200 MW | completed | 2019-04 | MISO |
| Morocco to Beecher 138 kV line | Hybrid | 200 MW | withdrawn | 2021-08 | MISO |
| Other_ | Wind | 200 MW | active | 2025-09 | MISO |
| BEECHER - SEEMLESS EAST 138.0kV | Solar | 190 MW | active | 2025-08 | MISO |
| BEECHER - KNOWLES 138.0kV | Solar | 150 MW | withdrawn | 2024-04 | MISO |
| Par - Raisin Road 138kV Line | Solar | 150 MW | completed | 2017-06 | MISO |
| BEECHER - KNOWLES 138.0kV | Solar | 150 MW | active | 2024-04 | MISO |
| KNOWLES - MOORE ROAD 138.0kV | Solar | 150 MW | active | 2025-08 | MISO |
| MOROCCO - ALLEN JUNCTION 345.0kV | Wind | 112 MW | active | 2025-09 | MISO |
| Beecher-Cement City 138kV | Solar | 100 MW | withdrawn | 2022-09 | MISO |
| 345kV Allen Junction to Morocco | Solar | 100 MW | withdrawn | 2020-06 | MISO |
| Raisin - METC Tap 138kV Line Tap | Solar | 80 MW | withdrawn | 2018-03 | MISO |
How this county ranks
Lenawee County ranks #290 of 1,607 US counties by capacity currently queued, and #10 of 42 in Michigan.
Other Michigan counties in the queue
| County | Pending | Capacity queued |
|---|---|---|
| Monroe County | 7 | 3.9 GW |
| Huron County | 16 | 3.6 GW |
| Livingston County | 6 | 2.3 GW |
| Branch County | 7 | 2.3 GW |
| Van Buren County | 11 | 2.3 GW |
| Washtenaw County | 7 | 2.2 GW |
| Saginaw County | 10 | 1.8 GW |
| Genesee County | 4 | 1.4 GW |
Go deeper on Lenawee County
The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.
Open Lenawee County on the map County reports All of Michigan