Data centers and new power in Branch County, MI

2.3 GW of new power is waiting to connect to the grid in Branch County, MI — 7 active requests. Typical wait: 1.6 years. 5 projects are built, 5 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Branch County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Branch County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Branch County right now.

2.3 GW
of new power is waiting to connect
7 projects asked. Not yet approved. Roughly what 1.8 million homes use.
675 MW
has actually been built
5 projects switched on so far.
1.6 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 29%
  • Still waiting 41%
  • Withdrawn 29%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Branch County.

What kind of power is asking to connect

  • Natural gas 64%
  • Solar 36%

By capacity requested. Data as of 14 October 2026.

All the numbers

17 requests ever filed
Pending applications
7
of 17 ever filed
Capacity queued
2.3 GW
requested, not committed
Already built
675 MW
5 projects connected
Built vs decided
50.0%
5 withdrawn
Median wait
1.6 yr
for applications still pending
Connected capacity
641 MW
indicator, see note

Source: interconnection queues published by MISO. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built5675 MW29.4%
Still waiting72.3 GW41.2%
Withdrawn5430 MW29.4%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Natural gas11.4 GW
Solar6830 MW

Key dates for projects here

1 dated · next closes 2027-09-10 (MISO)
QueueWhat closesClosesStanding
MISOMISO DPP-2026 Definitive Planning Phase application deadline
Attachment X of the tariff and BPM-015.
2027-09-10confirmed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
HIPLENatural gas1.4 GWactive2025-03MISO
Other_Solar200 MWactive2024-12MISO
BARTON LAKE - BATAVIA 138.0kVSolar200 MWcompleted2020-06MISO
WAGNERSolar200 MWactive2025-09MISO
Wagner 138 kV SubstationWind150 MWwithdrawn2019-04MISO
Coldwater - Batavia 138kV LineSolar150 MWcompleted2019-04MISO
Batavia - Wagner 138kV LineSolar150 MWcompleted2019-04MISO
WAGNER - BATAVIA 138.0kVSolar150 MWactive2024-04MISO
WAGNERSolar100 MWwithdrawn2024-12MISO
BUTTERS - NEWTON (MI AVE) 138.0kVSolar100 MWcompleted2020-06MISO
NEWTONSolar100 MWactive2023-10MISO
COLDWATER - MOORE ROAD 138.0kVSolar100 MWactive2025-03MISO
Batavia 138kV SubstationSolar80 MWwithdrawn2018-03MISO
COLDWATER - MOORE ROAD 138.0kVSolar80 MWactive2025-03MISO
New Byers 138kVNot stated75 MWcompleted2024-08MISO

How Branch County compares

#160 in the US · #4 in MI

Branch County ranks #160 of 1,607 US counties by power waiting to connect, and #4 of 42 in Michigan.

CountyWaitingCapacity queued
Monroe County73.9 GW
Huron County163.6 GW
Livingston County62.3 GW
Van Buren County112.3 GW
Washtenaw County72.2 GW
Saginaw County101.8 GW
Genesee County41.4 GW
Lenawee County81.4 GW

Common questions about power in Branch County

How long does it take to get power for a data center in Branch County, MI?

The median wait for a project still in the interconnection queue in Branch County is 1.6 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 5 projects in Branch County have reached energization and 5 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Branch County, MI?

2.3 GW is currently requested across 7 active interconnection requests, and 675 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Branch County, MI a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Michigan policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Branch County — MISO — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Branch County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Branch County on the map County reports All of Michigan