Data centers and new power in Wicomico County, MD

7 MW of new power is waiting to connect to the grid in Wicomico County, MD — 1 active requests. Typical wait: 5.2 years. 4 projects are built, 27 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Wicomico County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Wicomico County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Wicomico County right now.

7 MW
of new power is waiting to connect
1 projects asked. Not yet approved. Roughly what 6,000 homes use.
38 MW
has actually been built
4 projects switched on so far.
5.2 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 12%
  • Still waiting 3%
  • Withdrawn 82%
  • Paused 3%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Wicomico County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

33 requests ever filed
Pending applications
1
of 33 ever filed
Capacity queued
7 MW
requested, not committed
Already built
38 MW
4 projects connected
Built vs decided
12.9%
27 withdrawn
Median wait
5.2 yr
for applications still pending
Connected capacity
32 MW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built438 MW12.1%
Still waiting17 MW3.0%
Withdrawn27445 MW81.8%
Paused1—3.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar17 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Mt. Hermon 69 kVSolar75 MWwithdrawn2022-03PJM
Piney Grove-New Church 138kVNot stated55 MWwithdrawn2014-04PJM
Hebron 69kVSolar46 MWsuspended2017-01PJM
Hebron 69 kV IISolar46 MWwithdrawn2021-03PJM
Ocean Pines-Walston Switch 69kVSolar30 MWwithdrawn2016-04PJM
Laurel 69kVSolar20 MWwithdrawn2010-04PJM
Delmar 12kVSolar20 MWwithdrawn2010-08PJM
Fruitland 69kVSolar20 MWwithdrawn2011-11PJM
Vienna-Laurel 69kVSolar20 MWwithdrawn2014-10PJM
Rockawalkin 69kVSolar20 MWwithdrawn2016-04PJM
Mt. Hermon 23 kVSolar20 MWwithdrawn2021-06PJM
North Salisbury-Worcester 69kVBiomass16 MWwithdrawn2013-04PJM
New HopeSolar15 MWwithdrawn2012-04PJM
Rockawalkin 69kVSolar15 MWcompleted2013-03PJM
Rockawalkin 69 kVSolar15 MWcompleted2019-09PJM

How Wicomico County compares

#1235 in the US · #13 in MD

Wicomico County ranks #1235 of 1,607 US counties by power waiting to connect, and #13 of 22 in Maryland.

Common questions about power in Wicomico County

How long does it take to get power for a data center in Wicomico County, MD?

The median wait for a project still in the interconnection queue in Wicomico County is 5.2 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 4 projects in Wicomico County have reached energization and 27 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Wicomico County, MD?

7 MW is currently requested across 1 active interconnection requests, and 38 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Wicomico County, MD a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Maryland policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Wicomico County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Wicomico County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Wicomico County on the map County reports All of Maryland