Data centers and new power in Garrett County, MD

675 MW of new power is waiting to connect to the grid in Garrett County, MD — 3 active requests. Typical wait: 6.0 years. 5 projects are built, 19 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Garrett County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Garrett County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Garrett County right now.

675 MW
of new power is waiting to connect
3 projects asked. Not yet approved. Roughly what 540,000 homes use.
340 MW
has actually been built
5 projects switched on so far.
6.0 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 19%
  • Still waiting 11%
  • Withdrawn 70%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Garrett County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

27 requests ever filed
Pending applications
3
of 27 ever filed
Capacity queued
675 MW
requested, not committed
Already built
340 MW
5 projects connected
Built vs decided
20.8%
19 withdrawn
Median wait
6.0 yr
for applications still pending
Connected capacity
414 MW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built5340 MW18.5%
Still waiting3675 MW11.1%
Withdrawn19894 MW70.4%
Paused0—0.0%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar3675 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Friendsville 500 kVNatural gas432 MWwithdrawn2000-06PJM
Black Oak-Hatfield 500 kVSolar300 MWactive2020-09PJM
Mount Storm-Pruntytown 500kVSolar200 MWactive2021-09PJM
Albright-Mt. Zion 138 kVSolar175 MWactive2020-03PJM
Kelso Gap 138 kVWind100 MWcompleted2002-01PJM
Kelso Gap 138kVWind100 MWcompleted2003-07PJM
Hazelton-Jennings 138kVWind69 MWwithdrawn2014-08PJM
Four Mile Ridge Wind 138kVWind60 MWcompleted2008-06PJM
Deep Creek-Penn Mar 115kVWind60 MWwithdrawn2012-02PJM
AG1-078Solar60 MWwithdrawn2020-07PJM
Garrett CountyWind50 MWcompleted2008-07PJM
Roth Rock 138kVWind40 MWwithdrawn2005-01PJM
Kelso Gap 138kVWind30 MWcompleted2007-08PJM
Elbow MountainWind20 MWwithdrawn2008-06PJM
Garrett-Jenning 34.5kVWind20 MWwithdrawn2013-10PJM

How Garrett County compares

#524 in the US · #2 in MD

Garrett County ranks #524 of 1,607 US counties by power waiting to connect, and #2 of 22 in Maryland.

Common questions about power in Garrett County

How long does it take to get power for a data center in Garrett County, MD?

The median wait for a project still in the interconnection queue in Garrett County is 6.0 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 5 projects in Garrett County have reached energization and 19 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Garrett County, MD?

675 MW is currently requested across 3 active interconnection requests, and 340 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Garrett County, MD a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Maryland policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Garrett County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.