Data centers and new power in Dorchester County, MD

13 MW of new power is waiting to connect to the grid in Dorchester County, MD — 2 active requests. Typical wait: 6.5 years. 3 projects are built, 35 withdrawn. Data as of 14 October 2026.

Live here?

Is one near your house?

We have not mapped a large AI data center inside Dorchester County itself — but we track the biggest ones nationally, and requests to connect new power here are on the public record.

Free. Your address is used for one distance and is not stored.

The power picture

What is happening with electricity in Dorchester County

Every new power plant, battery or big customer has to join a waiting list before it can plug into the grid. This is what that list looks like in Dorchester County right now.

13 MW
of new power is waiting to connect
2 projects asked. Not yet approved. Roughly what 10,000 homes use.
104 MW
has actually been built
3 projects switched on so far.
6.5 yrs
typical wait to plug in

Where every request ever filed here ended up

  • Built 7%
  • Still waiting 5%
  • Withdrawn 85%
  • Paused 2%

Most requests in the US are withdrawn — a developer tests a site and moves on. That is normal, not a warning sign for Dorchester County.

What kind of power is asking to connect

  • Solar 100%

By capacity requested. Data as of 14 October 2026.

All the numbers

41 requests ever filed
Pending applications
2
of 41 ever filed
Capacity queued
13 MW
requested, not committed
Already built
104 MW
3 projects connected
Built vs decided
7.9%
35 withdrawn
Median wait
6.5 yr
for applications still pending
Connected capacity
310 MW
indicator, see note

Source: interconnection queues published by PJM. Parsed and normalised by Watt Street. Data as of 14 October 2026. A queued project is a request, not a commitment.

Outcome of every request filed here

OutcomeProjectsCapacityShare
Built3104 MW7.3%
Still waiting213 MW4.9%
Withdrawn351.7 GW85.4%
Paused1—2.4%

Waiting to connect, by type of power

TypeProjectsCapacity requested
Solar213 MW

Key dates for projects here

no dated windows published
QueueWhat closesClosesStanding
PJMDominion GS-5 (Virginia SCC PUR-2025-00058) - ESAs signed on or after this date carry the 14-year term
From this date the GS-5 large-load tariff carries a 14-year minimum term, alongside the reported 85% of contracted transmission demand minimum and $1…
No date published yetdisputed source
FERCFERC large-load show cause — stakeholder comments on RTO responses
Comments on the six RTO/ISO responses to the FPA section 206 show-cause orders of 18 June 2026 (PJM EL26-67, SPP EL26-68, NYISO EL26-69, MISO EL26-70…
No date published yetunconfirmed source
FERCFERC RM26-4 — generic large-load rulemaking
Still at ANOPR stage.
No date published yetconfirmed source
FERCGeorgia PSC - Georgia Power must file large-load contracts 30 days before execution
A standing obligation rather than a dated one: large-load contracts must be filed with the commission at least 30 days before they are executed.
No date published yetconfirmed source

A date marked confirmed was checked by a person against the authority's own tariff, order or form page. Anything else is listed so you know it exists, with a link so you can check it yourself. Full calendar.

The biggest projects on file

top 15 by size
ProjectTypeCapacityStatusFiledQueue
Vienna 230kVNatural gas750 MWwithdrawn2001-05PJM
Airey-Vienna 69 kV IIBatteries125 MWwithdrawn2020-09PJM
Airey-Vienna 69 kVSolar100 MWwithdrawn2020-03PJM
Vienna 138 kVBatteries100 MWwithdrawn2020-03PJM
Airey-Golden Hill 69 kVBatteries67 MWwithdrawn2019-09PJM
Airey 69 kVSolar56 MWwithdrawn2019-03PJM
Cambridge-West Cambridge 69kVSolar51 MWcompleted2016-04PJM
Todd 69kVSolar50 MWcompleted2016-04PJM
East New Market 69kVSolar50 MWsuspended2016-10PJM
Todd 69 kVSolar50 MWwithdrawn2021-01PJM
Todd 69 kVSolar50 MWwithdrawn2023-03PJM
Airey - Golden Hill 69 kVSolar28 MWwithdrawn2021-02PJM
West Cambridge - Vienna 69 kVSolar28 MWwithdrawn2021-03PJM
Todd 25kVSolar20 MWwithdrawn2011-01PJM
Dorchester CountySolar20 MWwithdrawn2011-03PJM

How Dorchester County compares

#1231 in the US · #12 in MD

Dorchester County ranks #1231 of 1,607 US counties by power waiting to connect, and #12 of 22 in Maryland.

Common questions about power in Dorchester County

How long does it take to get power for a data center in Dorchester County, MD?

The median wait for a project still in the interconnection queue in Dorchester County is 6.5 years. Across the US, most large loads are quoted three to seven years depending on the market and whether network upgrades are needed. 3 projects in Dorchester County have reached energization and 35 were withdrawn, so the withdrawal rate here is a better guide to risk than any single quoted timeline.

How much capacity is available in Dorchester County, MD?

13 MW is currently requested across 2 active interconnection requests, and 104 MW has actually been built. A queued megawatt is a request, not deliverable capacity — most queued projects are never built. For deliverable offtake capacity at a specific substation you need a utility study, not a queue.

Is Dorchester County, MD a good site for a data center?

This page gives you the power half of that answer: what is queued, what has been energized, how long the wait runs, and which large load interconnection requests are already recorded nearby. The other half — the state policy position, moratoriums and large load tariffs — is on our Maryland policy page.

Where does the data on this page come from?

The interconnection queue published by the transmission providers serving Dorchester County — PJM — parsed and normalised by Watt Street. Every figure carries the date it was true. Data as of 14 October 2026.

Go deeper on Dorchester County

The interactive map plots every one of these applications, and a generated county report puts them in a sourced PDF with the date each figure was true on every page.

Open Dorchester County on the map County reports All of Maryland